LNG Atlas

Country

Poland: LNG infrastructure

Poland has 2 LNG terminals and 54 tracked gas pipelines in the Global Energy Monitor tracker. It is an importer, with 6.1 Mtpa of operating regasification capacity and no operating liquefaction.

Export capacity

—

no export terminal tracked

Import capacity

6.1 Mtpa

4.48 Mtpa under construction

Pipelines

54

9,096 km tracked

Fleet

0

0 owned from here (flag not reported this release)

Import and export balance

DirectionTerminalsOperatingUnder construction
Export (liquefaction)0——
Import (regasification)26.14.48

Figures are whole-terminal capacities in Mtpa, not adjusted for ownership stakes or utilisation.

LNG terminals in Poland

Import / exportTypeUnits
Polish Baltic Sea Coast FSRUImportFSRUUnder construction4.48 Mtpaunder construction2—
Świnoujście Polskie LNG TerminalWojewództwoImportNot reportedOperating6.1 Mtpa32016

Gas pipelines crossing Poland

Any pipeline whose country list includes this country, including transit pipelines that only pass through.

CountriesSegments
Baltic Pipe ProjectNorway, Denmark, Sweden, PolandOperating613 km10 bcm/y12022
Baltic Pipe ProjectPomerania → LubuszPolandOperating122 kmNot reported12022
Baltic Pipe ProjectLubusz → Nowy TomyślPolandOperating69 kmNot reported12022
Bonikowo–Lwowek Gas PipelinePolandOperating156 kmNot reported1—
Czech-Polish Interconnector Gas Pipeline (CPI)Czechia, PolandProposed207 kmNot reported12022
Czeszów-Kiełczów Gas PipelinePolandOperating33 kmNot reported12018
Gas Interconnection Poland-LithuaniaPoland, LithuaniaOperating508 km2.4 bcm/y12022
Gas Interconnection Poland-LithuaniaPoland, LithuaniaOperating0 kmNot reported12024
Goleniow–Gdynia Gas PipelinePolandOperating278 kmNot reported1—
Goleniow–Szczecin Gas PipelinePolandOperating31 kmNot reported1—
Goleniów–Płoty Gas PipelinePolandOperating42 kmNot reported12022
Gustorzyn-Wronów Gas PipelinePolandOperating308 kmNot reported12023
Hermanowice-Jaroslaw PipelinePolandProposed39 kmNot reported12029
Hermanowice-Strachocina PipelinePolandOperating72 kmNot reported12020
Holowczyce–Pulawy Gas PipelinePolandOperating133 kmNot reported1—
Jaroslaw-Rozwadów PipelinePolandProposed60 kmNot reported12029
Kobryn-Brest-Warsaw Gas PipelineBelarus, PolandOperating263 km10 bcm/y11985
Kędzierzyn-Racibórz Gas PipelinePolandOperating37 kmNot reported12025
Lasow–Odolanow Gas PipelinePolandOperating235 kmNot reported1—
Lewin Brzeski-Nysa PipelineOpolskie Voivodeship → Opolskie VoivodeshipPolandProposed38 kmNot reported12020
Lwówek-Odlonów Gas PipelinePolandOperating168 kmNot reported12019
Odolanow-Latynia Gas PipelinePolandOperating113 kmNot reported1—
Odolanow–Husow Gas PipelinePolandOperating411 kmNot reported1—
Oswiecim–Pogorska Wola Gas PipelinePolandOperating147 kmNot reported1—
Oświęcim-Tworzen Gas PipelinePolandOperating44 kmNot reported12025
Pelczyce-Poznan Gas PipelinePolandOperating211 kmNot reported1—
Pogórska-Wola-Tworzen Gas PipelinePolandOperating168 kmNot reported12022
Poland-Slovakia Gas PipelinePoland, SlovakiaOperating165 km5.7 bcm/y12022
Poland-Slovakia Gas PipelinePoland, SlovakiaOperating0 km5.7 bcm/y12024
Poland-Ukraine Interconnector Gas PipelinePoland, UkraineCancelled110 km8 bcm/y12022
Poznan-Krobia Gas PipelinePolandOperating78 kmNot reported1—
Racibórz–Oświęcim Gas PipelinePolandUnder construction116 kmNot reported12026
Rembelszczyzna-Mory Gas PipelinePolandOperating29 kmNot reported12025
Rembelszczyzna-Wronów Gas PipelinePolandProposed135 kmNot reported12029
Rozwadów-Końskowola-Wronów PipelinePolandProposed120 kmNot reported12029
Rozwadów-Strachocina Gas PipelinePolandProposed160 kmNot reported12030
Skoczów-Komorowice-Oświęcim Gas PipelinePolandProposed58 kmNot reported1—
Stalowa Wola-Pogorska Wola Gas PipelinePolandOperating142 kmNot reported1—
Strachocina-Pogórska-Wola Gas PipelinePolandOperating97 kmNot reported12021
Strachocina-Pogórska-Wola Gas PipelinePolandOperating0 kmNot reported12024
Swinoujscie–Goleniow Gas PipelinePolandOperating60 kmNot reported1—
Szczecin - Lwówek to Dolna Odra Gas PipelinePolandOperating63 kmNot reported12023
Tworzen–Cieszyn Gas PipelinePolandOperating92 kmNot reported1—
Tworóg-Tworzen Gas PipelinePolandOperating55 kmNot reported12021
Tworórog-Kędzierzyn Gas PipelinePolandOperating43 kmNot reported12020
Volkovysk–Gosgranitza Gas PipelineBelarus, PolandOperating92 km2 bcm/y11974
Wloclawek–Gdynia Gas PipelinePolandOperating200 kmNot reported1—
Wloclawek–Odolanow Gas PipelinePolandOperating166 kmNot reported1—
Wloclawek–Rembelszczyzna Gas PipelinePolandOperating150 kmNot reported1—
Wronow–Husow Gas PipelinePolandOperating181 kmNot reported1—
Wronow–Jaroslaw Gas PipelinePolandOperating30 kmNot reported1—
Yamal Europe 2 PipelineBelarus, Poland, SlovakiaCancelled460 km15 bcm/y12019
Yamal-Europe Gas PipelineRussia, Belarus, Germany, PolandIdle1,660 km33 bcm/y11999
Zdzieszowice-Wrocław Gas PipelinePolandOperating130 kmNot reported12021

Chokepoint exposure

Chokepoint exposure is shown on each terminal page, taken from a hand-maintained trade-lane table. It is an editorial routing model of typical laden voyages, not vessel tracking. The exposure feed aggregates it by chokepoint.

Neighbouring countries

Countries that share a land border with this one and have tracked LNG infrastructure.

More countries in Europe

Ordered by number of tracked terminals, so countries next to each other here are of similar scale. The region is the one Global Energy Monitor gives this country's terminals.

In our rankings

Where this appears in the site's generated top lists. Each ranking page states its own method before its table.

Share this page:XLinkedInFacebookBlueskyRedditEmail