Gas transmission pipeline · Pogórska Wola to Tworzen
Pogórska-Wola-Tworzen Gas Pipeline
Pogórska-Wola-Tworzen Gas Pipeline is an operating gas transmission pipeline in Poland. The tracker lists 1 tracked segment, 168 km long, starting up in 2022. It runs from Pogórska Wola to Tworzen. It is owned by Gaz-System.
Length
168 km
Capacity
Not reported
Segments tracked
1
Largest diameter 1000 mm (39 in)
Route
Pogórska-Wola-Tworzen Gas Pipeline runs from Pogórska Wola to Tworzen. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Pogórska Wola
- To
- Tworzen
- Start country
- Poland
- End country
- Poland
- Countries crossed
- Poland
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Europe
- Route drawn on map
- 149 km
- GEM pipeline ID
- P1352
- Start year
- 2022
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Whole pipeline | Operating | Pogórska Wola → Tworzen | 168 | Not reported | 1000 mm | 2022 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
No tracked LNG terminal lies within 25 km of this pipeline's route.
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Owners
- Gaz-System100%
Parent companies
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does Pogórska-Wola-Tworzen Gas Pipeline run?
- Pogórska-Wola-Tworzen Gas Pipeline runs from Pogórska Wola to Tworzen, crossing Poland.
- How long is Pogórska-Wola-Tworzen Gas Pipeline?
- Pogórska-Wola-Tworzen Gas Pipeline is 168 km long.
- How much gas can Pogórska-Wola-Tworzen Gas Pipeline carry?
- No design capacity is reported for Pogórska-Wola-Tworzen Gas Pipeline. That is an absent figure, not a zero.
- Is Pogórska-Wola-Tworzen Gas Pipeline operating?
- Pogórska-Wola-Tworzen Gas Pipeline is operating, having started in 2022.
- Who owns Pogórska-Wola-Tworzen Gas Pipeline?
- Pogórska-Wola-Tworzen Gas Pipeline is owned by Gaz-System, as recorded in the current tracker release.