Pakistan: LNG infrastructure
Pakistan has 11 LNG terminals and 70 tracked gas pipelines in the Global Energy Monitor tracker. It is an importer, with 9.8 Mtpa of operating regasification capacity and no operating liquefaction.
Export capacity
—
no export terminal tracked
Import capacity
9.8 Mtpa
operating regasification
Pipelines
70
18,596 km tracked
Fleet
0
0 owned from here (flag not reported this release)
Import and export balance
| Direction | Terminals | Operating | Under construction |
|---|---|---|---|
| Export (liquefaction) | 0 | — | — |
| Import (regasification) | 11 | 9.8 | — |
Figures are whole-terminal capacities in Mtpa, not adjusted for ownership stakes or utilisation.
LNG terminals in Pakistan
| Import / export | Type | Units | ||||
|---|---|---|---|---|---|---|
| Daewoo Gas LNG TerminalBalochistan | Import | Not reported | Shelved | Not reported | 1 | — |
| Energas FSRUSindh | Import | FSRU | Proposed | 5.75 Mtpaproposed | 1 | — |
| Engro Elengy FSRUSindh | Import | FSRU | Operating | 4.8 Mtpa | 2 | 2015 |
| Engro FSRU 2Sindh | Import | FSRU | Cancelled | Not reported | 1 | — |
| GEIL FSRUSindh | Import | FSRU | Cancelled | Not reported | 1 | — |
| GasPort FSRUSindh | Import | FSRU | Operating | 5 Mtpa | 1 | 2017 |
| GasPort FSRU 2 | Import | FSRU | Proposed | 0.69 Mtpaproposed | 1 | — |
| LNG Easy Floating LNG Terminal | Import | Floating | Shelved | Not reported | 1 | — |
| Mashal LNG TerminalSindh | Import | Not reported | Cancelled | Not reported | 1 | — |
| Pakistan State Oil LNG Terminal | Import | Not reported | Shelved | Not reported | 1 | — |
| Tabeer LNG TerminalSindh | Import | Floating | Proposed | Not reported | 2 | — |
Gas pipelines crossing Pakistan
Any pipeline whose country list includes this country, including transit pipelines that only pass through.
| Countries | Segments | |||||
|---|---|---|---|---|---|---|
| AV22-Kot Addu Gas PipelinePunjab → Punjab | Pakistan | Operating | 70 km | Not reported | 1 | — |
| AV29-N2 RLNG PipelinePunjab → Punjab | Pakistan | Operating | 68 km | Not reported | 1 | — |
| AV29-Sahiwal Gas PipelinePunjab → Punjab | Pakistan | Operating | 145 km | Not reported | 1 | — |
| Badin Gas PipelineSindh → Sindh | Pakistan | Operating | 101 km | 2.04 bcm/y | 1 | 1988 |
| Bajara-Karachi LooplineSindh → Sindh | Pakistan | Operating | 200 km | 2.45 bcm/y | 1 | — |
| D.G. Khan Gas PipelinePunjab → Punjab | Pakistan | Operating | 72 km | Not reported | 1 | — |
| Dadu-Malir-Karachi Gas PipelineSindh → Sindh | Pakistan | Operating | 250 km | 4.09 bcm/y | 1 | — |
| Dadu-Sui Gas PipelineSindh → Balochistan | Pakistan | Operating | 266 km | 1.74 bcm/y | 1 | — |
| Dakhni-Meyal-Dhulian Gas PipelinePunjab → Punjab | Pakistan | Operating | 50 km | Not reported | 1 | — |
| Dandot-Gali Jagir-Wah Gas Pipeline IPunjab → Punjab | Pakistan | Operating | 154 km | Not reported | 1 | — |
| Dandot-Gali Jagir-Wah Gas Pipeline IIPunjab → Punjab | Pakistan | Operating | 152 km | Not reported | 1 | — |
| Dhodak-Kot Addu Gas PipelinePunjab → Punjab | Pakistan | Operating | 78 km | Not reported | 1 | — |
| Dhulian-Daud Khel Gas PipelinePunjab → Punjab | Pakistan | Operating | 85 km | Not reported | 1 | — |
| Faisalabad-Malakwal Gas PipelinePunjab → Punjab | Pakistan | Operating | 159 km | Not reported | 1 | — |
| Faisalabad-Malakwal Gas Pipeline IIPunjab → Punjab | Pakistan | Operating | 91 km | Not reported | 1 | — |
| Faisalabad-Shahdara Gas Pipeline-IPunjab → Punjab | Pakistan | Operating | 119 km | Not reported | 1 | — |
| Faisalabad-Shahdara Gas Pipeline-IIPunjab → Punjab | Pakistan | Operating | 113 km | Not reported | 1 | — |
| Gujrat-Jhelum Gas PipelinePunjab → Punjab | Pakistan | Operating | 54 km | Not reported | 1 | — |
| Gurguri-Kohat Gas PipelineKhyber Pakhtunkhwa → Khyber Pakhtunkhwa | Pakistan | Operating | 78 km | Not reported | 1 | — |
| HQ2-Tando Adam Gas PipelineSindh → Sindh | Pakistan | Operating | 81 km | 0.87 bcm/y | 1 | — |
| Haripur-Mansehra Gas PipelineKhyber Pakhtunkhwa → Khyber Pakhtunkhwa | Pakistan | Operating | 71 km | Not reported | 1 | — |
| Hassan-Sui Gas PipelineSindh → Balochistan | Pakistan | Operating | 58 km | 0.31 bcm/y | 1 | — |
| Head Balloki-MP 59.91 Gas PipelinePunjab → Punjab | Pakistan | Operating | 52 km | Not reported | 1 | — |
| Iran-Pakistan PipelineBushehr → Sindh | Iran, Pakistan | Under construction | 2,775 km | 7.67 bcm/y | 1 | 2024 |
| Iran-Pakistan-India PipelineBushehr → India | Iran, Pakistan, India | Cancelled | 2,700 km | 39.7 bcm/y | 1 | — |
| Jauharabad-Chashma Gas PipelinePunjab → Punjab | Pakistan | Operating | 82 km | Not reported | 1 | — |
| Kadanwari-Malir-Karachi Gas PipelineSindh → Sindh | Pakistan | Operating | 412 km | 1.84 bcm/y | 1 | — |
| Kandhkot Gas PipelineSindh → Sindh | Pakistan | Operating | 55 km | Not reported | 1 | — |
| Karachi–Sawan Gas PipelineSindh → Sindh | Pakistan | Operating | 371 km | 12.3 bcm/y | 1 | 2018 |
| Kohat-Nowshera Gas PipelineKhyber Pakhtunkhwa → Khyber Pakhtunkhwa | Pakistan | Operating | 86 km | Not reported | 1 | — |
| Kot Momin-Jauharabad Gas PipelinePunjab → Punjab | Pakistan | Operating | 72 km | Not reported | 1 | — |
| Krapa-Manjiwala Gas PipelineKhyber Pakhtunkhwa → Khyber Pakhtunkhwa | Pakistan | Operating | 84 km | Not reported | 1 | — |
| MP 59.91-Nandipur Power Plant Gas PipelinePunjab → Punjab | Pakistan | Operating | 76 km | Not reported | 1 | — |
| Manjiwala-Pezu Gas PipelineKhyber Pakhtunkhwa → Khyber Pakhtunkhwa | Pakistan | Operating | 53 km | Not reported | 1 | — |
| Mardan-Swat Gas PipelineKhyber Pakhtunkhwa → Khyber Pakhtunkhwa | Pakistan | Operating | 105 km | Not reported | 1 | — |
| Mian Channu-Hasilpur Gas PipelinePunjab → Punjab | Pakistan | Operating | 84 km | Not reported | 1 | — |
| N2-Sahiwal RLNG PipelinePunjab → Punjab | Pakistan | Operating | 77 km | Not reported | 1 | — |
| Nawabshah-Karachi Gas PipelineSindh → Sindh | Pakistan | Operating | 290 km | 0.82 bcm/y | 1 | — |
| Nowshera-Mardan-Takht Bhai-Sakhakot Gas PipelineKhyber Pakhtunkhwa → Khyber Pakhtunkhwa | Pakistan | Operating | 58 km | Not reported | 1 | — |
| Off-Shore Gas Pipeline | Pakistan, Iran | Proposed | 1,500 km | 10.2 bcm/y | 1 | — |
| Pakistan Stream Gas Pipeline | Pakistan | Proposed | 1,100 km | 12.4 bcm/y | 1 | 2024 |
| Phool Nagar-Dawood Hercules Gas LooplinePunjab → Punjab | Pakistan | Operating | 65 km | Not reported | 1 | — |
| Phool Nagar-Dawood Hercules Gas PipelinePunjab → Punjab | Pakistan | Operating | 62 km | Not reported | 1 | — |
| Pir Koh- Sui Gas PipelineBalochistan → Balochistan | Pakistan | Operating | 71 km | Not reported | 1 | — |
| Qadirpur Gas LooplineSindh → Punjab | Pakistan | Operating | 53 km | Not reported | 1 | — |
| Qadirpur Gas PipelineSindh → Punjab | Pakistan | Operating | 53 km | Not reported | 1 | — |
| Qadirpur Gas Pipeline (LNG Phase II)Sindh → Punjab | Pakistan | Operating | 53 km | Not reported | 1 | — |
| Quetta Gas PipelineSindh → Balochistan | Pakistan | Operating | 344 km | 0.92 bcm/y | 1 | — |
| Rawat-Murree Gas PipelineIslamabad → Punjab | Pakistan | Operating | 57 km | Not reported | 1 | — |
| SV1-QV1 Gas PipelineSindh → Sindh | Pakistan | Operating | 131 km | Not reported | 1 | — |
| Sahiwal-Akhtar Abad Gas PipelinePunjab → Punjab | Pakistan | Operating | 67 km | Not reported | 1 | — |
| Sahiwal-Lahore Gas Pipeline IPunjab → Punjab | Pakistan | Operating | 143 km | Not reported | 1 | — |
| Sahiwal-Lahore Gas Pipeline-IIPunjab → Punjab | Pakistan | Operating | 77 km | Not reported | 1 | — |
| Sakhakot-Swat Gas PipelineKhyber Pakhtunkhwa → Khyber Pakhtunkhwa | Pakistan | Operating | 68 km | Not reported | 1 | — |
| Sawan- Qadirpur Gas PipelineSindh → Sindh | Pakistan | Operating | 131 km | Not reported | 1 | — |
| Sawan–Lahore Gas PipelineSindh → Punjab | Pakistan | Under construction | 770 km | 12.3 bcm/y | 1 | 2025 |
| Shahdara-Gujranwala-Rahwali Gas PipelinePunjab → Punjab | Pakistan | Operating | 73 km | Not reported | 1 | — |
| Sheikhupura-Gujranwala Gas PipelinePunjab → Punjab | Pakistan | Operating | 59 km | Not reported | 1 | — |
| Sidhnai-Faisalabad Gas PipelinePunjab → Punjab | Pakistan | Operating | 164 km | Not reported | 1 | — |
| Sidhnai-Faisalabad Gas Pipeline IIPunjab → Punjab | Pakistan | Operating | 130 km | Not reported | 1 | — |
| Sindh University to FJFC Offtake LooplineSindh → Sindh | Pakistan | Operating | 116 km | 0.61 bcm/y | 1 | — |
| Somiani–Nawabshah Gas PipelineBalochistan → Sindh | Pakistan | Shelved | 310 km | 12.3 bcm/y | 1 | — |
| Sui-Multan Gas Loopline IBalochistan → Punjab | Pakistan | Operating | 314 km | Not reported | 1 | — |
| Sui-Multan Gas Loopline IIPunjab → Punjab | Pakistan | Operating | 257 km | Not reported | 1 | — |
| Sui-Multan Gas Loopline IIIPunjab → Punjab | Pakistan | Operating | 214 km | Not reported | 1 | — |
| Sui-Multan Gas PipelineBalochistan → Punjab | Pakistan | Operating | 288 km | Not reported | 1 | — |
| Turkmenistan-Afghanistan-Pakistan-India Gas PipelineAhal → Punjab | Turkmenistan, Afghanistan, Pakistan, India | Under construction | 1,814 km | 33 bcm/y | 1 | — |
| Wah-Nowshera Gas Pipeline IPunjab → Khyber Pakhtunkhwa | Pakistan | Operating | 50 km | Not reported | 1 | — |
| Wah-Nowshera Gas Pipeline IIPunjab → Khyber Pakhtunkhwa | Pakistan | Operating | 53 km | Not reported | 1 | — |
| Zarghun-Quetta Gas PipelineBalochistan → Balochistan | Pakistan | Operating | 61 km | 0.26 bcm/y | 1 | 2014 |
Chokepoint exposure
Chokepoint exposure is shown on each terminal page, taken from a hand-maintained trade-lane table. It is an editorial routing model of typical laden voyages, not vessel tracking. The exposure feed aggregates it by chokepoint.
Neighbouring countries
Countries that share a land border with this one and have tracked LNG infrastructure.
More countries in Asia
Ordered by number of tracked terminals, so countries next to each other here are of similar scale. The region is the one Global Energy Monitor gives this country's terminals.
In our rankings
Where this appears in the site's generated top lists. Each ranking page states its own method before its table.