Export terminal · Louisiana, United States
Calcasieu Pass LNG Terminal
Calcasieu Pass LNG Terminal is an operating LNG export terminal in Louisiana, United States. The tracker lists 1 tracked unit with 10 Mtpa operating, the earliest starting in 2022. It is owned by Venture Global Calcasieu Pass LLC.
Operating
10 Mtpa
13.6 bcm/y · 1 unit
Under construction
—
no units under construction
Proposed
—
no units proposed
At a glance
- Country
- United States
- State / province
- Louisiana
- Region
- Americas
- Import / export
- Export
- Onshore / floating
- Not reported
- Status (rolled up)
- Operating
- Trains / phases tracked
- 1
- Earliest start year
- 2022
- Latest start year
- 2022
- Coordinates
- 29.7729° N, 93.3343° W
- GEM terminal ID
- T100000130212
- GEM wiki page
- gem.wiki
Trains and phases
Each row is one unit as tracked by GEM. Ordered by start year, then proposal year.
| Unit | Status | Capacity (Mtpa) | Capacity (bcm/y) | Start | Proposed | FID | Owner (as reported) |
|---|---|---|---|---|---|---|---|
| T1-T18 | Operating | 10 | 13.6 | 2022 | — | Not reported | Venture Global Calcasieu Pass LLC [100%] |
Capacity by status
| Status | Units | Mtpa | bcm/y |
|---|---|---|---|
| Operating | 1 | 10 | 13.6 |
Owners and operators
Stakes as reported by GEM per unit, merged across units. Percentages are omitted where GEM does not give them.
Owners
Parent companies
Operators
Reported cost
Global Energy Monitor's estimated cost for each unit that reports one, converted to US dollars. Estimates at the date GEM last updated the unit, not adjusted for inflation.
| Unit | Status | Capacity | Estimated cost | Per tonne a year |
|---|---|---|---|---|
| T1-T18 | Operating | 10 Mtpa | $7.1 billion | $710 |
Financing as GEM records it: US$2 billion equity investment from Venture Global LNG and Stonepeak Infrastructure Partners; US$5.7 billion in loans from a consortium of international banks; Part of a US$500 million loan from Bank of America, JPMorgan Chase, Mizuho and Morgan Stanley which Venture Global LNG secured in February 2021 was reported to be going to the Calcasieu Pass project;In August 2021, Venture Global LNG completed a US$2.5 billion bond offering, the proceeds of which are principally to prepay certain amounts outstanding under its existing loans for the project;In May 2023, Venture Global closed a US$4.5 billion offering of senior secured notes;In October and November 2023, Venture Global closed US$4 billion and US$1 billion in senior notes offerings, respectively
A unit with no cost reported is not shown, and the figures are never added across statuses. How the estimates compare is on project costs.
Power, vessels and projects tied to this terminal
Low-carbon projects recorded
- Carbon capture and storage
A project is recorded against the terminal; that does not mean it is built or running. See all terminals with low-carbon projects recorded.
Location
Calcasieu Pass LNG Terminal at 29.7729° N, 93.3343° W, with 44 tracked gas pipelines passing within 25 km.
Loads about 250 kB of map code and the country outline file.
- Coordinates
- 29.7729° N, 93.3343° W
- Coordinate accuracy (GEM)
- exact
- Open in OpenStreetMap
- View on map
Connected gas pipelines
Tracked pipelines whose route passes within 25 km of this terminal, or whose name matches it. Proximity is not proof of a physical connection.
| Pipeline | Status | Length | Capacity | Distance | Matched by |
|---|---|---|---|---|---|
| Bridgeline Gas Pipeline | Operating | 1,585 km | 9.4 bcm/y | 1.6 km | route proximity |
| TransCameron Pipeline | Operating | 39 km | 19.42 bcm/y | 2.6 km | route proximity |
| CP Express Pipeline | Under construction | 147 km | 40.88 bcm/y | 2.7 km | route proximity |
| Kinetica Energy Express | Operating | 1,139 km | — | 3.1 km | route proximity |
| ANR Gas Pipeline | Operating | 2,897 km | 61.32 bcm/y | 3.9 km | route proximity |
| ANR Gas Pipeline | Operating | 0 km | 1.69 bcm/y | 3.9 km | route proximity |
| ANR Gas Pipeline | Proposed | 0 km | 1.28 bcm/y | 3.9 km | route proximity |
| ANR Gas Pipeline | Under construction | 0 km | 4.29 bcm/y | 3.9 km | route proximity |
| ANR Gas Pipeline | Proposed | 0 km | 0.74 bcm/y | 3.9 km | route proximity |
| ANR Gas Pipeline | Proposed | 1 km | 0 bcm/y | 3.9 km | route proximity |
| Creole Trail Pipeline | Operating | 151 km | 15.33 bcm/y | 3.9 km | route proximity |
| Creole Trail Pipeline | Proposed | 0 km | 9.5 bcm/y | 3.9 km | route proximity |
| Natural Gas Pipeline Company of America System | Operating | 14,645 km | 16.35 bcm/y | 7.7 km | route proximity |
| Natural Gas Pipeline Company of America System | Proposed | 0 km | 3.18 bcm/y | 7.7 km | route proximity |
| Columbia Gulf Transmission Pipeline | Operating | 5,360 km | — | 10.4 km | route proximity |
| Transcontinental Gas Pipeline | Operating | 10,200 km | 171.7 bcm/y | 10.6 km | route proximity |
| Transcontinental Gas Pipeline | Under construction | 0 km | 0.66 bcm/y | 10.6 km | route proximity |
| Transcontinental Gas Pipeline | Cancelled | 1 km | 1.94 bcm/y | 10.6 km | route proximity |
| Transcontinental Gas Pipeline | Cancelled | 10 km | 2.5 bcm/y | 10.6 km | route proximity |
| Transcontinental Gas Pipeline | Proposed | 13 km | 3.03 bcm/y | 10.6 km | route proximity |
| Transcontinental Gas Pipeline | Operating | 0 km | 4.85 bcm/y | 10.6 km | route proximity |
| Transcontinental Gas Pipeline | Operating | 0 km | 3.72 bcm/y | 10.6 km | route proximity |
| Transcontinental Gas Pipeline | Proposed | 0 km | 9.71 bcm/y | 10.6 km | route proximity |
| Transcontinental Gas Pipeline | Under construction | 0 km | 0.65 bcm/y | 10.6 km | route proximity |
| Transcontinental Gas Pipeline | Proposed | 0 km | 1.18 bcm/y | 10.6 km | route proximity |
| Transcontinental Gas Pipeline | Proposed | 26 km | 1.85 bcm/y | 10.6 km | route proximity |
| Tennessee Gas Pipeline | Operating | 18,926 km | 10.22 bcm/y | 19.1 km | route proximity |
| Tennessee Gas Pipeline | Operating | 0 km | 9.14 bcm/y | 19.1 km | route proximity |
| Tennessee Gas Pipeline | Cancelled | 1,551 km | — | 19.1 km | route proximity |
| Tennessee Gas Pipeline | Cancelled | 547 km | 13.29 bcm/y | 19.1 km | route proximity |
| Gulf South Gas Pipeline | Operating | 12,070 km | 27.59 bcm/y | 22 km | route proximity |
| Gulf South Gas Pipeline | Operating | 0 km | 0.49 bcm/y | 22 km | route proximity |
| Gulf South Gas Pipeline | Operating | 6 km | 2.04 bcm/y | 22 km | route proximity |
| Gulf South Gas Pipeline | Operating | 29 km | 10.22 bcm/y | 22 km | route proximity |
| Gulf South Gas Pipeline | Operating | 26 km | 7.51 bcm/y | 22 km | route proximity |
| Gulf South Gas Pipeline | Operating | 0 km | 5.68 bcm/y | 22 km | route proximity |
| Gulf South Gas Pipeline | Operating | 113 km | 5.22 bcm/y | 22 km | route proximity |
| Gulf South Gas Pipeline | Operating | 0 km | 2.56 bcm/y | 22 km | route proximity |
| Gulf South Gas Pipeline | Operating | 47 km | 2.41 bcm/y | 22 km | route proximity |
| Gulf South Gas Pipeline | Operating | 0 km | 2.04 bcm/y | 22 km | route proximity |
| Gulf South Gas Pipeline | Proposed | 3 km | 2.41 bcm/y | 22 km | route proximity |
| Gulf South Gas Pipeline | Proposed | 0 km | 1.23 bcm/y | 22 km | route proximity |
| Gulf South Gas Pipeline | Proposed | 0 km | 2.86 bcm/y | 22 km | route proximity |
| Stingray Gas Pipeline | Operating | 523 km | 12.26 bcm/y | 22.8 km | route proximity |
Vessels owned by the same companies
Ships in the tracker held by a company that also owns, operates or parents this terminal. A shared owner is not the same as a dedicated trade.
| Vessel | Via | Status | Capacity | Delivered |
|---|---|---|---|---|
| Hull 2541 (Hanwha) | Venture Global LNG | Under construction | 200,000 m³ | 2026 |
| Hull 2542 (Hanwha) | Venture Global LNG | Under construction | 200,000 m³ | 2026 |
| Hull 2543 (Hanwha) | Venture Global LNG | Under construction | 200,000 m³ | 2026 |
| Hull 2574 (Hanwha) | Venture Global LNG | Under construction | 200,000 m³ | 2026 |
| Hull 2575 (Hanwha) | Venture Global LNG | Under construction | 200,000 m³ | 2026 |
| Venture Bayou | Venture Global LNG | Operating | 174,000 m³ | 2024 |
| Venture Gator | Venture Global LNG | Operating | 174,000 m³ | 2024 |
Exposed to chokepoints
Where cargoes from this terminal would normally pass a maritime chokepoint, by destination market.
| Destination | Chokepoints on the usual route | Alternative route |
|---|---|---|
| East Asia | Panama CanalPanama slot availability and draught decide between these; the Cape is the fallback. | Suez CanalStrait of Malacca |
| South Asia | Suez CanalBab el-Mandeb | Cape of Good Hope |
Routing is an editorial model of typical laden voyages, held in a hand-maintained lane table. It is not vessel tracking, and it does not account for diversions, canal draught limits, ice class or seasonal closures. See methodology, browse every chokepoint, or take the machine-readable exposure feed.
In the news
Recent headlines that name Calcasieu Pass LNG Terminal. Matched by name, so it is approximate. Titles and links only; we store no article text.
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where is Calcasieu Pass LNG Terminal?
- Calcasieu Pass LNG Terminal is an LNG export terminal in Louisiana, United States. It is made up of 1 tracked train or phase.
- Is Calcasieu Pass LNG Terminal operating?
- Calcasieu Pass LNG Terminal is operating, with its first tracked train starting in 2022.
- How much LNG can Calcasieu Pass LNG Terminal handle?
- Calcasieu Pass LNG Terminal has 10 Mtpa operating, equivalent to 13.6 bcm/y of gas a year in operation. Capacity at different statuses is never added together.
- Who owns Calcasieu Pass LNG Terminal?
- Calcasieu Pass LNG Terminal is owned by Venture Global Calcasieu Pass LLC, and operated by Venture Global Calcasieu Pass LLC. Shares are as recorded in the current tracker release.
- Which maritime chokepoints do cargoes from Calcasieu Pass LNG Terminal pass?
- Cargoes from Calcasieu Pass LNG Terminal would normally pass Panama Canal, Suez Canal, Bab el-Mandeb, Strait of Malacca and 1 other. This is an editorial model of typical laden voyages by destination market, not vessel tracking, and any individual cargo may go another way.
- What pipelines connect to Calcasieu Pass LNG Terminal?
- 44 tracked gas pipelines pass within 25 km of Calcasieu Pass LNG Terminal. Proximity is not proof of a physical connection; each match is listed with its distance.
In our rankings
Where this appears in the site's generated top lists. Each ranking page states its own method before its table.
Cite this page
Reuse is welcome; please name the page and the tracker release it draws on.