Louisiana Energy Access Project Pipeline is an operating gas transmission pipeline in United States. The tracker lists 1 tracked segment, 241 km long and 10.22 bcm/y of capacity, starting up in 2020. It runs from Haynesville to Gillis Hub. It is owned by DT Midstream Inc.
Length
241 km
Capacity
10.2 bcm/y
7.5 Mtpa LNG equivalent
Segments tracked
1
Largest diameter 914 mm (36 in)
Route
Louisiana Energy Access Project Pipeline runs from Haynesville to Gillis Hub. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Haynesville
- To
- Gillis Hub
- Start country
- United States
- End country
- United States
- Countries crossed
- United States
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Americas
- Route drawn on map
- 368 km
- GEM pipeline ID
- P5113
- Start year
- 2020
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Whole pipeline | Operating | Haynesville → Gillis Hub | 241 | 10.2 | 914 mm | 2020 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
| Terminal | Country | Import / export | Status | Distance | Matched by |
|---|---|---|---|---|---|
| Andes Energy LNG Terminal | Colombia | Import | Proposed | — | name match |
| Arrow Energy LNG Terminal | Australia | Export | Cancelled | — | name match |
| Batangas Clean Energy LNG Terminal | Philippines | Import | Cancelled | — | name match |
| Cambodia LNG Project | Cambodia | Import | Cancelled | — | name match |
| Caofeidian LNG Terminal (Beijing Energy) | China | Import | Cancelled | — | name match |
| Fermeuse Energy FLNG Terminal | Canada | Export | Proposed | — | name match |
| Filipinas LNG Gateway Project FSRU | Philippines | Import | Shelved | — | name match |
| H-Energy Kakinada LNG Terminal | India | Import | Cancelled | — | name match |
| Ingleside Energy LNG Terminal | United States | Export | Cancelled | — | name match |
| Jade Energy LNG Terminal | Germany | Import | Proposed | — | name match |
| Jiangyin LNG Terminal (Zhongtian Energy) | China | Import | Shelved | — | name match |
| Liuheng LNG Terminal (Zhejiang Energy) | China | Import | Under construction | — | name match |
| Louisiana LNG Terminal | United States | Export | Cancelled | — | name match |
| Louisiana Offshore Oil Port | United States | Export | Operating | — | name match |
| Main Pass Energy Hub FLNG Terminal | United States | Export | Cancelled | — | name match |
| NewTimes Energy LNG Terminal | Canada | Export | Cancelled | — | name match |
| Project Venezuela LNG Terminal | Venezuela | Export | Cancelled | — | name match |
| Safe Harbor Energy LNG Terminal | United States | Import | Cancelled | — | name match |
| Stewart Energy LNG Terminal | Canada | Export | Cancelled | — | name match |
| Woodside Louisiana LNG Terminal | United States | Export | Under construction | — | name match |
| Yakutia LNG Project | Russia | Export | Shelved | — | name match |
| Zeeland Energy FSRU | Netherlands | Import | Proposed | — | name match |
| Zhangzhou LNG Terminal (China Energy Reserve) | China | Import | Cancelled | — | name match |
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Owners
- DT Midstream Inc100%
Parent companies
- DT Midstream Inc100%
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does Louisiana Energy Access Project Pipeline run?
- Louisiana Energy Access Project Pipeline runs from Haynesville to Gillis Hub, crossing United States.
- How long is Louisiana Energy Access Project Pipeline?
- Louisiana Energy Access Project Pipeline is 241 km long.
- How much gas can Louisiana Energy Access Project Pipeline carry?
- Louisiana Energy Access Project Pipeline has a design capacity of 10.2 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
- Is Louisiana Energy Access Project Pipeline operating?
- Louisiana Energy Access Project Pipeline is operating, having started in 2020.
- Who owns Louisiana Energy Access Project Pipeline?
- Louisiana Energy Access Project Pipeline is owned by DT Midstream Inc, as recorded in the current tracker release.
- Does Louisiana Energy Access Project Pipeline serve an LNG terminal?
- Louisiana Energy Access Project Pipeline passes within 25 km of 23 tracked LNG terminals. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.