Azerbaijan has 13 tracked gas pipelines in the Global Energy Monitor tracker. It operates no LNG terminal capacity, and none is under construction.
Export capacity
—
no export terminal tracked
Import capacity
—
no import terminal tracked
Pipelines
13
6,603 km tracked
Fleet
0
0 owned from here (flag not reported this release)
Import and export balance
| Direction | Terminals | Operating | Under construction |
|---|---|---|---|
| Export (liquefaction) | 0 | — | — |
| Import (regasification) | 0 | — | — |
Figures are whole-terminal capacities in Mtpa, not adjusted for ownership stakes or utilisation.
Gas pipelines crossing Azerbaijan
Any pipeline whose country list includes this country, including transit pipelines that only pass through.
| Countries | Segments | |||||
|---|---|---|---|---|---|---|
| Azerbaijan-Georgia-Romania Interconnector Gas Pipeline (AGRI) | Azerbaijan, Georgia | Cancelled | 920 km | 8 bcm/y | 1 | 2027 |
| Bahar-Hovsan-Surakhani Gas Pipeline | Azerbaijan | Operating | 45 km | 1.8 bcm/y | 1 | 2009 |
| Hajigabul-Gazakh-Saguramo Pipeline | Azerbaijan, Georgia | Operating | 478 km | 8.7 bcm/y | 1 | 2006 |
| Hajigabul-Shirvanovka-Mozdok Pipeline | Russia, Azerbaijan | Operating | 680 km | 10 bcm/y | 1 | 1982 |
| Hajiqabul–Astara–Abadan Gas PipelineHajiqabul → Khuzestan | Azerbaijan, Iran | Operating | 1,475 km | 10 bcm/y | 1 | 1970 |
| Iğdır-Nakhchivan Gas PipelineIğdır → Nakhchivan | Türkiye, Azerbaijan | Operating | 157 km | 0.73 bcm/y | 1 | 2024 |
| Neft Dashlary-Bahar Gas Pipeline | Azerbaijan | Operating | 67 km | 5.5 bcm/y | 1 | 2007 |
| Rasht-Chelavend Gas Pipeline | Iran, Azerbaijan | Operating | 150 km | 5.5 bcm/y | 1 | 2024 |
| South Caucasus Gas Pipeline | Azerbaijan, Georgia, Türkiye | Operating | 693 km | 7.41 bcm/y | 1 | 2006 |
| South Caucasus Gas Pipeline | Azerbaijan, Georgia, Türkiye | Operating | 489 km | 16.6 bcm/y | 1 | 2018 |
| South Caucasus Gas Pipeline | Azerbaijan, Georgia, Türkiye | Shelved | 1,150 km | 7 bcm/y | 1 | — |
| Trans-Caspian Gas Pipeline | Turkmenistan, Azerbaijan | Proposed | 300 km | 16 bcm/y | 1 | 2029 |
| Trans-Caspian Gas Pipeline | Turkmenistan, Azerbaijan | Proposed | 0 km | 14 bcm/y | 1 | — |
Chokepoint exposure
Chokepoint exposure is shown on each terminal page, taken from a hand-maintained trade-lane table. It is an editorial routing model of typical laden voyages, not vessel tracking. The exposure feed aggregates it by chokepoint.
Neighbouring countries
Countries that share a land border with this one and have tracked LNG infrastructure.
In our rankings
Where this appears in the site's generated top lists. Each ranking page states its own method before its table.