Gas transmission pipeline · Sangachal Terminal to Kulevi

Azerbaijan-Georgia-Romania Interconnector Gas Pipeline (AGRI)

Azerbaijan-Georgia-Romania Interconnector Gas Pipeline (AGRI) is a cancelled gas transmission pipeline crossing Azerbaijan, Georgia. The tracker lists 1 tracked segment, 920 km long and 8 bcm/y of capacity, starting up in 2027. It runs from Sangachal Terminal to Kulevi. Owners include SNGN RomGaz SA, Government of Azerbaijan, Georgian Oil and Gas Corp and 1 more.

Length

920 km

Capacity

8 bcm/y

5.9 Mtpa LNG equivalent

Segments tracked

1

Route

Azerbaijan-Georgia-Romania Interconnector Gas Pipeline (AGRI) runs from Sangachal Terminal to Kulevi. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Sangachal Terminal
To
Kulevi
Start country
Azerbaijan
End country
Georgia
Countries crossed
Azerbaijan, Georgia
Onshore / offshore
Not reported
Fuel
Gas
Region
Asia
Route drawn on map
692 km
GEM pipeline ID
P0735
Start year
2027
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineCancelledSangachal Terminal → Kulevi92082027GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

TerminalCountryImport / exportStatusDistanceMatched by
Kulevi LNG TerminalGeorgiaImportCancelled1.2 kmroute proximity

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Azerbaijan-Georgia-Romania Interconnector Gas Pipeline (AGRI) run?
Azerbaijan-Georgia-Romania Interconnector Gas Pipeline (AGRI) runs from Sangachal Terminal to Kulevi, crossing Azerbaijan and Georgia.
How long is Azerbaijan-Georgia-Romania Interconnector Gas Pipeline (AGRI)?
Azerbaijan-Georgia-Romania Interconnector Gas Pipeline (AGRI) is 920 km long.
How much gas can Azerbaijan-Georgia-Romania Interconnector Gas Pipeline (AGRI) carry?
Azerbaijan-Georgia-Romania Interconnector Gas Pipeline (AGRI) has a design capacity of 8 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is Azerbaijan-Georgia-Romania Interconnector Gas Pipeline (AGRI) operating?
Azerbaijan-Georgia-Romania Interconnector Gas Pipeline (AGRI) is cancelled, with a reported start year of 2027.
Who owns Azerbaijan-Georgia-Romania Interconnector Gas Pipeline (AGRI)?
Azerbaijan-Georgia-Romania Interconnector Gas Pipeline (AGRI) is owned by Georgian Oil and Gas Corp, Government of Azerbaijan, MVM Group and 1 other, as recorded in the current tracker release.
Does Azerbaijan-Georgia-Romania Interconnector Gas Pipeline (AGRI) serve an LNG terminal?
Azerbaijan-Georgia-Romania Interconnector Gas Pipeline (AGRI) passes within 25 km of 1 tracked LNG terminal. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.