South Tunisia Gas Project Pipelines

South Tunisia Gas Project Pipelines is an under construction gas transmission pipeline in Tunisia. The tracker lists 1 tracked segment, 94 km long and 6132 bcm/y of capacity. It runs from Tataouine to Tataouine.

Length

94 km

Capacity

6132 bcm/y

4508.8 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 305 mm (12 in)

Route

South Tunisia Gas Project Pipelines runs from Tataouine to Tataouine. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Tataouine
To
Tataouine
Start country
Tunisia
End country
Tunisia
Countries crossed
Tunisia
Onshore / offshore
Not reported
Fuel
Gas
Region
Not reported
Route drawn on map
431 km
GEM pipeline ID
P7651
Start year
Not reported
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Tataouine Gas PipelineUnder constructionTataouine → Tataouine946132305 mm—GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

TerminalCountryImport / exportStatusDistanceMatched by
Cambodia LNG ProjectCambodiaImportCancelled—name match
Filipinas LNG Gateway Project FSRUPhilippinesImportUnder construction—name match
PAWA PNG FSRU ProjectPapua New GuineaImportShelved—name match
Project Venezuela LNG TerminalVenezuelaExportCancelled—name match
Yakutia LNG ProjectRussiaExportProposed—name match

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Ownership is not reported for this pipeline.

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does South Tunisia Gas Project Pipelines run?
South Tunisia Gas Project Pipelines runs from Tataouine to Tataouine, crossing Tunisia.
How long is South Tunisia Gas Project Pipelines?
South Tunisia Gas Project Pipelines is 94 km long.
How much gas can South Tunisia Gas Project Pipelines carry?
South Tunisia Gas Project Pipelines has a design capacity of 6132 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is South Tunisia Gas Project Pipelines operating?
South Tunisia Gas Project Pipelines is under construction.
Who owns South Tunisia Gas Project Pipelines?
Ownership of South Tunisia Gas Project Pipelines is not reported in the current tracker release.
Does South Tunisia Gas Project Pipelines serve an LNG terminal?
South Tunisia Gas Project Pipelines passes within 25 km of 5 tracked LNG terminals. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.

More gas pipelines in Tunisia

Listed in name order among the 16 pipelines tracked in Tunisia, so projects with the same name sit together. A browse aid, not a claim that they are alike.