LNG Chain

Gas transmission pipeline · Guwahati to Itanagar, Agartala, Imphal

North East Natural Gas Pipeline Grid Project

North East Natural Gas Pipeline Grid Project is an under construction gas transmission pipeline in India. The tracker lists 1 tracked segment, 1,656 km long and 1.73 bcm/y of capacity, starting up in 2026. It runs from Guwahati to Itanagar, Agartala, Imphal. It is owned by Indradhanush Gas Grid Ltd (IGGL).

Length

1,656 km

Capacity

1.73 bcm/y

1.3 Mtpa LNG equivalent

Segments tracked

1

Route

North East Natural Gas Pipeline Grid Project runs from Guwahati to Itanagar, Agartala, Imphal. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Guwahati
To
Itanagar, Agartala, Imphal
Start country
India
End country
India
Countries crossed
India
Onshore / offshore
Not reported
Fuel
Gas
Region
Asia
Route drawn on map
1,251 km
GEM pipeline ID
P1309
Start year
2026
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineUnder constructionGuwahati → Itanagar, Agartala, Imphal1,6561.732026GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

TerminalCountryImport / exportStatusDistanceMatched by
Cambodia LNG ProjectCambodiaImportCancelledname match
Filipinas LNG Gateway Project FSRUPhilippinesImportShelvedname match
Project Venezuela LNG TerminalVenezuelaExportCancelledname match
Yakutia LNG ProjectRussiaExportShelvedname match

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does North East Natural Gas Pipeline Grid Project run?
North East Natural Gas Pipeline Grid Project runs from Guwahati to Itanagar, Agartala, Imphal, crossing India.
How long is North East Natural Gas Pipeline Grid Project?
North East Natural Gas Pipeline Grid Project is 1,656 km long.
How much gas can North East Natural Gas Pipeline Grid Project carry?
North East Natural Gas Pipeline Grid Project has a design capacity of 1.73 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is North East Natural Gas Pipeline Grid Project operating?
North East Natural Gas Pipeline Grid Project is under construction, with a reported start year of 2026.
Who owns North East Natural Gas Pipeline Grid Project?
North East Natural Gas Pipeline Grid Project is owned by Indradhanush Gas Grid Ltd (IGGL), as recorded in the current tracker release.
Does North East Natural Gas Pipeline Grid Project serve an LNG terminal?
North East Natural Gas Pipeline Grid Project passes within 25 km of 4 tracked LNG terminals. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.