Gas transmission pipeline · Córdoba to Boyacá
VIM - Interior
VIM - Interior is a proposed gas transmission pipeline in Colombia. The tracker lists 1 tracked segment, 300 km long and 1.02 bcm/y of capacity, starting up in 2027. It runs from Córdoba to Boyacá.
Length
300 km
Capacity
1.02 bcm/y
0.8 Mtpa LNG equivalent
Segments tracked
1
Route
VIM - Interior runs from Córdoba to Boyacá. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Córdoba
- To
- Boyacá
- Start country
- Colombia
- End country
- Colombia
- Countries crossed
- Colombia
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Not reported
- Route drawn on map
- 301 km
- GEM pipeline ID
- P7569
- Start year
- 2027
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Jobo-Vasconia | Proposed | Córdoba → Boyacá | 300 | 1.02 | — | 2027 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
No tracked LNG terminal lies within 25 km of this pipeline's route.
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Ownership is not reported for this pipeline.
In the news
Recent headlines that name VIM - Interior. Matched by name, so it is approximate. Titles and links only; we store no article text.
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does VIM - Interior run?
- VIM - Interior runs from Córdoba to Boyacá, crossing Colombia.
- How long is VIM - Interior?
- VIM - Interior is 300 km long.
- How much gas can VIM - Interior carry?
- VIM - Interior has a design capacity of 1.02 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
- Is VIM - Interior operating?
- VIM - Interior is proposed, with a reported start year of 2027.
- Who owns VIM - Interior?
- Ownership of VIM - Interior is not reported in the current tracker release.
More gas pipelines in Colombia
Listed in name order among the 39 pipelines tracked in Colombia, so projects with the same name sit together. A browse aid, not a claim that they are alike.
- Bogotá - SNT Magdalena MedioCundinamarca to Tolima · 105 km
- Buenaventura-Yumbo Gas PipelineValle del Cauca to Valle del Cauca · 100 km
- Cúcuta - SNT Magdalena MedioNorte de Santander to Cesar · 100 km
- TGI Pipeline NetworkHuila to Huila · 3,505 km
- TransmetanoSantander to Antioquia · 190 km
- TransoccidenteValle del Cauca to Valle del Cauca · 11 km
Cite this page