Gas transmission pipeline · Tuxpan to Dos Bocas
Southeast Gateway Gas Pipeline
Southeast Gateway Gas Pipeline is an operating gas transmission pipeline in Mexico. The tracker lists 1 tracked segment, 715 km long and 13.29 bcm/y of capacity, starting up in 2025. It runs from Tuxpan to Dos Bocas. It is owned by TC Energy Corp and Comisión Federal de Electricidad.
Length
715 km
Capacity
13.3 bcm/y
9.8 Mtpa LNG equivalent
Segments tracked
1
Largest diameter 914 mm (36 in)
Route
Southeast Gateway Gas Pipeline runs from Tuxpan to Dos Bocas. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Tuxpan
- To
- Dos Bocas
- Start country
- Mexico
- End country
- Mexico
- Countries crossed
- Mexico
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Americas
- Route drawn on map
- 630 km
- GEM pipeline ID
- P3921
- Start year
- 2025
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Whole pipeline | Operating | Tuxpan → Dos Bocas | 715 | 13.3 | 914 mm | 2025 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
| Terminal | Country | Import / export | Status | Distance | Matched by |
|---|---|---|---|---|---|
| Coatzacoalcos II LNG Terminal | Mexico | Export | Proposed | 0 km | route proximity |
| Coatzacoalcos LNG Terminal (CFE) | Mexico | Export | Shelved | 0 km | route proximity |
| Filipinas LNG Gateway Project FSRU | Philippines | Import | Shelved | — | name match |
| Gulf Gateway Deepwater Port LNG Terminal | United States | Import | Retired | — | name match |
| Northeast Gateway LNG Terminal | United States | Import | Idle | — | name match |
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Owners
Parent companies
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does Southeast Gateway Gas Pipeline run?
- Southeast Gateway Gas Pipeline runs from Tuxpan to Dos Bocas, crossing Mexico.
- How long is Southeast Gateway Gas Pipeline?
- Southeast Gateway Gas Pipeline is 715 km long.
- How much gas can Southeast Gateway Gas Pipeline carry?
- Southeast Gateway Gas Pipeline has a design capacity of 13.3 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
- Is Southeast Gateway Gas Pipeline operating?
- Southeast Gateway Gas Pipeline is operating, having started in 2025.
- Who owns Southeast Gateway Gas Pipeline?
- Southeast Gateway Gas Pipeline is owned by TC Energy Corp and Comisión Federal de Electricidad, as recorded in the current tracker release.
- Does Southeast Gateway Gas Pipeline serve an LNG terminal?
- Southeast Gateway Gas Pipeline passes within 25 km of 5 tracked LNG terminals. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.