Guadalajara Gas Pipeline is an operating gas transmission pipeline in Mexico. The tracker lists 1 tracked segment, 313 km long and 8.79 bcm/y of capacity, starting up in 2011. It runs from Manzanillo to El Salto. It is owned by TC Energy Corp.

Length

313 km

Capacity

8.79 bcm/y

6.5 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 610 mm (24 in)

Route

Guadalajara Gas Pipeline runs from Manzanillo to El Salto. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Manzanillo
To
El Salto
Start country
Mexico
End country
Mexico
Countries crossed
Mexico
Onshore / offshore
Not reported
Fuel
Gas
Region
Americas
Route drawn on map
297 km
GEM pipeline ID
P1280
Start year
2011
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineOperatingManzanillo → El Salto3138.79610 mm2011GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

TerminalCountryImport / exportStatusDistanceMatched by
Gato Negro Manzanillo LNG TerminalMexicoExportProposed0.4 kmroute proximity
Manzanillo (Mexico) LNG TerminalMexicoImportOperating0.5 kmroute proximity

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Owners

Parent companies

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Guadalajara Gas Pipeline run?
Guadalajara Gas Pipeline runs from Manzanillo to El Salto, crossing Mexico.
How long is Guadalajara Gas Pipeline?
Guadalajara Gas Pipeline is 313 km long.
How much gas can Guadalajara Gas Pipeline carry?
Guadalajara Gas Pipeline has a design capacity of 8.79 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is Guadalajara Gas Pipeline operating?
Guadalajara Gas Pipeline is operating, having started in 2011.
Who owns Guadalajara Gas Pipeline?
Guadalajara Gas Pipeline is owned by TC Energy Corp, as recorded in the current tracker release.
Does Guadalajara Gas Pipeline serve an LNG terminal?
Guadalajara Gas Pipeline passes within 25 km of 2 tracked LNG terminals. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.