LNG Atlas

Gas transmission pipeline · Louisiana to Louisiana

Gator Express Gas Pipeline

Gator Express Gas Pipeline is an under construction gas transmission pipeline in United States. The tracker lists 1 tracked segment, 24 km long and 20.13 bcm/y of capacity, starting up in 2024. It runs from Louisiana to Louisiana. It is owned by Gator Express Pipeline LLC.

Length

24 km

Capacity

20.1 bcm/y

14.8 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 1067 mm (42 in)

Route

Gator Express Gas Pipeline runs from Louisiana to Louisiana. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Louisiana
To
Louisiana
Start country
United States
End country
United States
Countries crossed
United States
Onshore / offshore
Not reported
Fuel
Gas
Region
Not reported
Route drawn on map
41 km
GEM pipeline ID
P0193
Start year
2024
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Phase IUnder constructionLouisiana → Louisiana2420.11067 mm2024GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

TerminalCountryImport / exportStatusDistanceMatched by
Plaquemines LNG TerminalUnited StatesExportOperating2.2 kmroute proximity
Delta LNG TerminalUnited StatesExportCancelled3.6 kmroute proximity
Gulfstream LNG TerminalUnited StatesExportProposed9.3 kmroute proximity

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Gator Express Gas Pipeline run?
Gator Express Gas Pipeline runs from Louisiana to Louisiana, crossing United States.
How long is Gator Express Gas Pipeline?
Gator Express Gas Pipeline is 24 km long.
How much gas can Gator Express Gas Pipeline carry?
Gator Express Gas Pipeline has a design capacity of 20.1 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is Gator Express Gas Pipeline operating?
Gator Express Gas Pipeline is under construction, with a reported start year of 2024.
Who owns Gator Express Gas Pipeline?
Gator Express Gas Pipeline is owned by Gator Express Pipeline LLC, as recorded in the current tracker release.
Does Gator Express Gas Pipeline serve an LNG terminal?
Gator Express Gas Pipeline passes within 25 km of 3 tracked LNG terminals. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.

More gas pipelines in United States

Listed in name order among the 515 pipelines tracked in United States, so projects with the same name sit together. A browse aid, not a claim that they are alike.

Cite this page

Reuse is welcome; please name the page and the tracker release it draws on.

BibTeX
Share this page:XLinkedInFacebookBlueskyRedditEmail