LNG Atlas

Ranking

LNG final investment decisions, by year

When LNG units reached the decision to build, when others plan to, how long a decision took to become a plant, and where decided units stand now. Units, not capacity; export and import apart.

Only 207 of 1,206 units say anything about FID

GEM records a final investment decision for 94 units and a plan to reach one for 113 more. For the other 999 the field is blank, which GEM defines as no information on FID. A blank is not a “no”, and it is the usual state of an older operating unit, so this page describes the units that report, not every unit. The year is the actual year of the decision for FID units and the planned year for pre-FID units, so the two are in separate tables.

A unit is one train or phase. Nothing here adds capacity: the capacity of any unit is on its terminal page, and capacity at different statuses is never combined.

Decisions taken, by year

Units marked FID, by the year GEM gives for the decision. 7 more are marked FID with no year and are not in the table.

Export (liquefaction) units marked final investment decision, by year of decision
02468102003: 120032004: 02005: 020052006: 12007: 120072008: 12009: 120092010: 02011: 120112012: 22013: 020132014: 12015: 420152016: 12017: 120172018: 22019: 1020192020: 12021: 220212022: 72023: 720232024: 52025: 92025
Show these figures as a table
YearExport units
20031
20040
20050
20061
20071
20081
20091
20100
20111
20122
20130
20141
20154
20161
20171
20182
201910
20201
20212
20227
20237
20245
20259

Use this chart

Embed it on your site

The image links back to this page and carries its data attribution line; please keep both.

Share this chart:XLinkedInFacebookBlueskyRedditEmail
FID yearExport unitsImport unitsOther or unclassifiedAll units
20031001
20061001
20071102
20081203
20091001
20111102
20122103
20141203
20154004
20161001
20171001
20182103
2019101011
20201001
202128010
202273010
20237209
20245308
202593113

Counts are units that are marked FID today, in whatever status they hold now: a unit cancelled after its decision is still counted in the year of that decision. Earlier years show few units because most older operating units have no FID status recorded at all, not because few decisions were taken.

Decisions planned, by year

Units still proposed that are marked pre-FID, by the year their developers plan to decide. 6 more are pre-FID with no planned year.

Planned FID yearExport unitsImport unitsAll unitsCompared with the release
2008101Already past
2021303Already past
2022134Already past
2023639Already past
2024505Already past
202525631Year of the release
202612214Still ahead
2027101Still ahead
2028303Still ahead

22 of these 71 units name a year before 2025 and are still proposed: a plan that slips is ordinary in this industry, and the table shows how much of the pipeline is in that state. It is not a forecast of what will be decided. For how plans move, see the construction timeline and build times.

Where units stand today

Units that report FID status, by their status now. Current status only: it does not say why a unit stopped.

Status todayMarked FIDMarked pre-FID
ExportImportExportImport
Operating231200
Under construction271040
Proposed1036215
Idle2100
Shelved2054
Cancelled12212

Units of a type that is neither export nor import are not shown. A unit marked pre-FID and under construction is as GEM reports it; the two fields are not reconciled here. GEM infers shelved after two years without development updates and cancelled after four; see cancelled and shelved.

How long a decision takes

Years from the year proposed to the year of FID, and from the year of FID to the year the unit started operating, for units that report both years. A group shows a summary from five units.

From proposal to FID

GroupUnitsMedianMiddle halfShortest to longest
Export (liquefaction)221.5 years1 year to 3.8 years0 to 11 years
Import (regasification)201.5 years0 years to 4 years0 to 7 years

From FID to operation

GroupUnitsMedianMiddle halfShortest to longest
Export (liquefaction)195 years3 years to 6.5 years1 to 7 years
Import (regasification)123 years2 years to 4 years1 to 6 years

Only operating units can be timed from FID to start, so these are the units that were finished. Floating units are not split out here because too few report both years; the build times page separates them. To read what an FID means, see the guide to reading a final investment decision.

Common questions

Each answer stands on its own.

In which year were the most LNG units taken to final investment decision?
2025, with 13 units (9 export, 3 import) among the 87 units that report both a final investment decision and its year in the September 2025 release. A unit is one train or phase, so a single plant can add several.
How many LNG units are marked as having reached FID?
94 of 1,206 units, and 113 more are marked pre-FID. The other 999 are blank, which GEM defines as no information on FID, not as a decision that has not been taken. Most operating units are blank, because their decision was taken long ago and was never recorded.
How long does it take from FID to start-up?
Among operating units that report both years, the median is 5 years for export (19 units) and 3 years for import (12 units). Only units that were finished can be timed, so this leaves out any that stalled after FID. Years are whole calendar years, so a figure can be a year out either way.
What does a planned FID year mean?
For a project marked pre-FID, GEM gives the year its developers plan to reach FID. It is a plan, not a forecast: 22 of the 71 proposed units that give one name a year before 2025, so the date has already gone by without the status changing.
Does reaching FID mean a plant gets built?
Mostly, in this data, but not always. 8 of the 94 units marked FID are now idle, shelved or cancelled; the outcomes table gives every status. It records current status only and does not say why a unit stopped.

Cite this page

Reuse is welcome; please name the page and the tracker release it draws on.

BibTeX
Share this page:XLinkedInFacebookBlueskyRedditEmail