LNG Atlas

Ranking

LNG capacity under construction, by planned start year

Terminal capacity being built, grouped by the start year Global Energy Monitor currently plans for each train or phase. Export and import are shown separately.

Read the years as plans, and note what is missing

A planned start year is a unit's latest plan, not a forecast. GEM reports one for only 44 of the89 units under construction, so a large share of the capacity below sits in a "not reported" row rather than in a year. Nothing is estimated to fill it.

Capacity is summed per unit, so a terminal with several trains appears once per train, in that train's own year. Under-construction capacity only: proposed and operating capacity are never added in.

Export (liquefaction)

Liquefaction capacity under construction, in million tonnes per year.

Export (liquefaction) capacity under construction by planned start year (Mtpa)
025502025: 1020252026: 22.820262027: 44.520272028: 39.720282029: 5.8720292030: 62030
Show these figures as a table
YearMtpa
202510
202622.8
202744.5
202839.7
20295.87
20306
Planned start yearUnitsTerminalsCapacity
20251110 Mtpa
20264322.8 Mtpa
20277744.5 Mtpa
20286539.7 Mtpa
2029115.87 Mtpa
2030116 Mtpa
Not reported12883.8 Mtpa

12 export units under construction report no planned start year, so they cannot be placed on the chart.

Import (regasification)

Regasification send-out capacity under construction, in million tonnes per year.

Import (regasification) capacity under construction by planned start year (Mtpa)
0102030402023: 0.320232024: 220242025: 30.120252026: 13.920262027: 34.820272028: 8.882028
Show these figures as a table
YearMtpa
20230.3
20242
202530.1
202613.9
202734.8
20288.88
Planned start yearUnitsTerminalsCapacity
2023110.3 Mtpa
2024222 Mtpa
20259930.1 Mtpa
20264413.9 Mtpa
20276634.8 Mtpa
2028228.88 Mtpa
Not reported3332108 Mtpa

33 import units under construction report no planned start year, so they cannot be placed on the chart.

Have the plans moved?

44 units under construction have both an original and a latest planned start year in the tracker. Of those, 42 are now planned for a later year than first planned, 0 for the same year and 2 for an earlier one. This counts only units where GEM reports both years, and says nothing about the units that report neither.

Every ingest of a new release is compared with the last one, so movement in these years will show up in what changed. The terminals themselves are in the under-construction directory, and the ships being built to serve them are on the carrier order book.

Common questions

Each answer stands on its own.

How much LNG capacity is under construction, and when is it due?
89 terminal units are under construction in the September 2025 release. Only 44 of them have a planned start year reported; the timeline groups those by year and shows the rest as not reported rather than guessing.
Is a planned start year a forecast?
No. It is the latest plan Global Energy Monitor holds for a unit, and plans slip. 3 units are still under construction with a planned year earlier than the 2025 release. Treat each year as reported, not expected.
Why are export and import capacity not added together?
Export capacity is liquefaction output and import capacity is regasification send-out. They measure different things at opposite ends of the chain, so this site always shows them separately.
Have planned start dates moved?
Of 44 units under construction with both an original and a latest planned start year, 42 are now planned later than first planned, 0 unchanged and 2 earlier.