Gas transmission pipeline · Yamalo-Nenets Autonomus Okrug to Chelyabinsk Oblast

Urengoy-Chelyabinsk Gas Pipeline

Urengoy-Chelyabinsk Gas Pipeline is an operating gas transmission pipeline in Russia. The tracker lists 1 tracked segment, 1,780 km long and 58 bcm/y of capacity, starting up in 1979. It runs from Yamalo-Nenets Autonomus Okrug to Chelyabinsk Oblast. It is owned by Gazprom PJSC.

Length

1,780 km

Capacity

58 bcm/y

42.6 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 36068 mm (1420 in)

Route

Urengoy-Chelyabinsk Gas Pipeline runs from Yamalo-Nenets Autonomus Okrug to Chelyabinsk Oblast. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Yamalo-Nenets Autonomus Okrug
To
Chelyabinsk Oblast
Start country
Russia
End country
Russia
Countries crossed
Russia
Onshore / offshore
Not reported
Fuel
Gas
Region
Not reported
Route drawn on map
1,740 km
GEM pipeline ID
P2440
Start year
1979
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineOperatingYamalo-Nenets Autonomus Okrug → Chelyabinsk Oblast1,7805836068 mm1979GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

No tracked LNG terminal lies within 25 km of this pipeline's route.

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Owners

Parent companies

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Urengoy-Chelyabinsk Gas Pipeline run?
Urengoy-Chelyabinsk Gas Pipeline runs from Yamalo-Nenets Autonomus Okrug to Chelyabinsk Oblast, crossing Russia.
How long is Urengoy-Chelyabinsk Gas Pipeline?
Urengoy-Chelyabinsk Gas Pipeline is 1,780 km long.
How much gas can Urengoy-Chelyabinsk Gas Pipeline carry?
Urengoy-Chelyabinsk Gas Pipeline has a design capacity of 58 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is Urengoy-Chelyabinsk Gas Pipeline operating?
Urengoy-Chelyabinsk Gas Pipeline is operating, having started in 1979.
Who owns Urengoy-Chelyabinsk Gas Pipeline?
Urengoy-Chelyabinsk Gas Pipeline is owned by Gazprom PJSC, as recorded in the current tracker release.

More gas pipelines in Russia

Listed in name order among the 266 pipelines tracked in Russia, so projects with the same name sit together. A browse aid, not a claim that they are alike.

Cite this page

Reuse is welcome; please name the page and the tracker release it draws on.

BibTeX
Share this page:XLinkedInFacebookBlueskyRedditEmail