Gas transmission pipeline · Yamalo-Nenets Autonomous Okrug to Tambov Oblast
Urengoy-Center Gas Pipeline
Urengoy-Center Gas Pipeline is an operating gas transmission pipeline in Russia. The tracker lists 1 tracked segment, 3,035 km long and 32.49 bcm/y of capacity, starting up in 1985. It runs from Yamalo-Nenets Autonomous Okrug to Tambov Oblast. It is owned by Gazprom PJSC.
Length
3,035 km
Capacity
32.5 bcm/y
23.9 Mtpa LNG equivalent
Segments tracked
1
Largest diameter 35560 mm (1400 in)
Route
Urengoy-Center Gas Pipeline runs from Yamalo-Nenets Autonomous Okrug to Tambov Oblast. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Yamalo-Nenets Autonomous Okrug
- To
- Tambov Oblast
- Start country
- Russia
- End country
- Russia
- Countries crossed
- Russia
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Not reported
- Route drawn on map
- 2,857 km
- GEM pipeline ID
- P5612
- Start year
- 1985
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| II | Operating | Yamalo-Nenets Autonomous Okrug → Tambov Oblast | 3,035 | 32.5 | 35560 mm | 1985 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
| Terminal | Country | Import / export | Status | Distance | Matched by |
|---|---|---|---|---|---|
| Yokkaichi LNG Center | Japan | Import | Operating | — | name match |
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Owners
- Gazprom PJSC100%
Parent companies
- Gazprom PJSC100%
In the news
Recent headlines that name Urengoy-Center Gas Pipeline. Matched by name, so it is approximate. Titles and links only; we store no article text.
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does Urengoy-Center Gas Pipeline run?
- Urengoy-Center Gas Pipeline runs from Yamalo-Nenets Autonomous Okrug to Tambov Oblast, crossing Russia.
- How long is Urengoy-Center Gas Pipeline?
- Urengoy-Center Gas Pipeline is 3,035 km long.
- How much gas can Urengoy-Center Gas Pipeline carry?
- Urengoy-Center Gas Pipeline has a design capacity of 32.5 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
- Is Urengoy-Center Gas Pipeline operating?
- Urengoy-Center Gas Pipeline is operating, having started in 1985.
- Who owns Urengoy-Center Gas Pipeline?
- Urengoy-Center Gas Pipeline is owned by Gazprom PJSC, as recorded in the current tracker release.
- Does Urengoy-Center Gas Pipeline serve an LNG terminal?
- Urengoy-Center Gas Pipeline passes within 25 km of 1 tracked LNG terminal. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.
More gas pipelines in Russia
Listed in name order among the 266 pipelines tracked in Russia, so projects with the same name sit together. A browse aid, not a claim that they are alike.
- Urengoy-Chelyabinsk Gas PipelineYamalo-Nenets Autonomus Okrug to Chelyabinsk Oblast · 1,780 km
- Urengoy-Chelyabinsk Gas PipelineChelyabinsk region to Chelyabinsk Oblast · 63 km
- Urengoy-Novopskov Gas PipelineYamalo-Nenets Autonomous Okrug to Luhansk · 3,609 km
- Ukhta-Torzhok (Yamal) 4 Gas PipelineRepublic of Komi to Vologda Oblast · 973 km
- Ukhta-Torzhok (Yamal) Gas PipelineRepublic of Komi to Vologda Oblast · 970 km
- Urengoy-Center Gas PipelineYamalo-Nenets Autonomous Okrug to Tambov Oblast · 3,211 km
Cite this page
Reuse is welcome; please name the page and the tracker release it draws on.