Gas transmission pipeline · Tas Yuryakh to Aykhal
Tas-Yuryakh-Mirny-Udachny Gas Pipeline
Tas-Yuryakh-Mirny-Udachny Gas Pipeline is an operating gas transmission pipeline in Russia. The tracker lists 1 tracked segment, 686 km long and 1 bcm/y of capacity, starting up in 2002. It runs from Tas Yuryakh to Aykhal. It is owned by Alrosa-Gas JSC.
Length
686 km
Capacity
1 bcm/y
0.7 Mtpa LNG equivalent
Segments tracked
1
Route
Tas-Yuryakh-Mirny-Udachny Gas Pipeline runs from Tas Yuryakh to Aykhal. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Tas Yuryakh
- To
- Aykhal
- Start country
- Russia
- End country
- Russia
- Countries crossed
- Russia
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Europe
- Route drawn on map
- 589 km
- GEM pipeline ID
- P2431
- Start year
- 2002
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Tas-Yuryakh-Mirny-Aykhal Gas Pipeline | Operating | Tas Yuryakh → Aykhal | 686 | 1 | — | 2002 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
No tracked LNG terminal lies within 25 km of this pipeline's route.
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Owners
- Alrosa-Gas JSC100%
Parent companies
- Alrosa PJSC100%
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does Tas-Yuryakh-Mirny-Udachny Gas Pipeline run?
- Tas-Yuryakh-Mirny-Udachny Gas Pipeline runs from Tas Yuryakh to Aykhal, crossing Russia.
- How long is Tas-Yuryakh-Mirny-Udachny Gas Pipeline?
- Tas-Yuryakh-Mirny-Udachny Gas Pipeline is 686 km long.
- How much gas can Tas-Yuryakh-Mirny-Udachny Gas Pipeline carry?
- Tas-Yuryakh-Mirny-Udachny Gas Pipeline has a design capacity of 1 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
- Is Tas-Yuryakh-Mirny-Udachny Gas Pipeline operating?
- Tas-Yuryakh-Mirny-Udachny Gas Pipeline is operating, having started in 2002.
- Who owns Tas-Yuryakh-Mirny-Udachny Gas Pipeline?
- Tas-Yuryakh-Mirny-Udachny Gas Pipeline is owned by Alrosa-Gas JSC, as recorded in the current tracker release.