LNG Chain

Gas transmission pipeline · Aykhal to Udachny

Tas-Yuryakh-Mirny-Udachny Gas Pipeline

Tas-Yuryakh-Mirny-Udachny Gas Pipeline is an under construction gas transmission pipeline in Russia. The tracker lists 1 tracked segment, 57 km long and 0.26 bcm/y of capacity, starting up in 2023. It runs from Aykhal to Udachny. It is owned by Alrosa-Gas JSC.

Length

57 km

Capacity

0.26 bcm/y

0.2 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 300 mm (12 in)

Route

Tas-Yuryakh-Mirny-Udachny Gas Pipeline runs from Aykhal to Udachny. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Aykhal
To
Udachny
Start country
Russia
End country
Russia
Countries crossed
Russia
Onshore / offshore
Not reported
Fuel
Gas
Region
Europe
Route drawn on map
59 km
GEM pipeline ID
P3175
Start year
2023
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Aykhal-Udachny Branch Gas PipelineUnder constructionAykhal → Udachny570.26300 mm2023GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

No tracked LNG terminal lies within 25 km of this pipeline's route.

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Owners

Parent companies

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Tas-Yuryakh-Mirny-Udachny Gas Pipeline run?
Tas-Yuryakh-Mirny-Udachny Gas Pipeline runs from Aykhal to Udachny, crossing Russia.
How long is Tas-Yuryakh-Mirny-Udachny Gas Pipeline?
Tas-Yuryakh-Mirny-Udachny Gas Pipeline is 57 km long.
How much gas can Tas-Yuryakh-Mirny-Udachny Gas Pipeline carry?
Tas-Yuryakh-Mirny-Udachny Gas Pipeline has a design capacity of 0.26 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is Tas-Yuryakh-Mirny-Udachny Gas Pipeline operating?
Tas-Yuryakh-Mirny-Udachny Gas Pipeline is under construction, with a reported start year of 2023.
Who owns Tas-Yuryakh-Mirny-Udachny Gas Pipeline?
Tas-Yuryakh-Mirny-Udachny Gas Pipeline is owned by Alrosa-Gas JSC, as recorded in the current tracker release.