LNG Atlas

Gas transmission pipeline · Kharkiv Oblast to Bryansk Oblast

Shebelinka-Belgorod-Kursk-Bryansk Gas Pipeline

Shebelinka-Belgorod-Kursk-Bryansk Gas Pipeline is an operating gas transmission pipeline crossing Russia, Ukraine. The tracker lists 1 tracked segment, 507 km long and 4.75 bcm/y of capacity, starting up in 1960. It runs from Kharkiv Oblast to Bryansk Oblast. It is owned by Gazprom PJSC.

Length

507 km

Capacity

4.75 bcm/y

3.5 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 25908 mm (1020 in)

Route

Shebelinka-Belgorod-Kursk-Bryansk Gas Pipeline runs from Kharkiv Oblast to Bryansk Oblast. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Kharkiv Oblast
To
Bryansk Oblast
Start country
Ukraine
End country
Russia
Countries crossed
Russia, Ukraine
Onshore / offshore
Not reported
Fuel
Gas
Region
Not reported
Route drawn on map
514 km
GEM pipeline ID
P2387
Start year
1960
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineOperatingKharkiv Oblast → Bryansk Oblast5074.7525908 mm1960GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

No tracked LNG terminal lies within 25 km of this pipeline's route.

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Owners

Parent companies

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Shebelinka-Belgorod-Kursk-Bryansk Gas Pipeline run?
Shebelinka-Belgorod-Kursk-Bryansk Gas Pipeline runs from Kharkiv Oblast to Bryansk Oblast, crossing Russia and Ukraine.
How long is Shebelinka-Belgorod-Kursk-Bryansk Gas Pipeline?
Shebelinka-Belgorod-Kursk-Bryansk Gas Pipeline is 507 km long.
How much gas can Shebelinka-Belgorod-Kursk-Bryansk Gas Pipeline carry?
Shebelinka-Belgorod-Kursk-Bryansk Gas Pipeline has a design capacity of 4.75 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is Shebelinka-Belgorod-Kursk-Bryansk Gas Pipeline operating?
Shebelinka-Belgorod-Kursk-Bryansk Gas Pipeline is operating, having started in 1960.
Who owns Shebelinka-Belgorod-Kursk-Bryansk Gas Pipeline?
Shebelinka-Belgorod-Kursk-Bryansk Gas Pipeline is owned by Gazprom PJSC, as recorded in the current tracker release.

More gas pipelines in Russia

Listed in name order among the 266 pipelines tracked in Russia, so projects with the same name sit together. A browse aid, not a claim that they are alike.

Cite this page

Reuse is welcome; please name the page and the tracker release it draws on.

BibTeX
Share this page:XLinkedInFacebookBlueskyRedditEmail