Gas transmission pipeline · New South Wales to New South Wales
Queensland Hunter Gas Pipeline
Queensland Hunter Gas Pipeline is a proposed gas transmission pipeline in Australia. The tracker lists 1 tracked segment, 60 km long and 2.01 bcm/y of capacity. It runs from New South Wales to New South Wales. It is owned by Hunter Gas Pipeline Pty Ltd.
Length
60 km
Capacity
2.01 bcm/y
1.5 Mtpa LNG equivalent
Segments tracked
1
Largest diameter 508 mm (20 in)
Route
Queensland Hunter Gas Pipeline runs from New South Wales to New South Wales. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- New South Wales
- To
- New South Wales
- Start country
- Australia
- End country
- Australia
- Countries crossed
- Australia
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Not reported
- Route drawn on map
- 49 km
- GEM pipeline ID
- P5896
- Start year
- Not reported
- Estimated cost (GEM, US dollars)
- $65.4 million
- Final investment decision
- 2025
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Narrabri Lateral Pipeline | Proposed | New South Wales → New South Wales | 60 | 2.01 | 508 mm | — | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
| Terminal | Country | Import / export | Status | Distance | Matched by |
|---|---|---|---|---|---|
| Queensland Curtis LNG Terminal | Australia | Export | Operating | — | name match |
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Owners
Parent companies
- Santos100%
In the news
Recent headlines that name Queensland Hunter Gas Pipeline. Matched by name, so it is approximate. Titles and links only; we store no article text.
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does Queensland Hunter Gas Pipeline run?
- Queensland Hunter Gas Pipeline runs from New South Wales to New South Wales, crossing Australia.
- How long is Queensland Hunter Gas Pipeline?
- Queensland Hunter Gas Pipeline is 60 km long.
- How much gas can Queensland Hunter Gas Pipeline carry?
- Queensland Hunter Gas Pipeline has a design capacity of 2.01 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
- Is Queensland Hunter Gas Pipeline operating?
- Queensland Hunter Gas Pipeline is proposed.
- Who owns Queensland Hunter Gas Pipeline?
- Queensland Hunter Gas Pipeline is owned by Hunter Gas Pipeline Pty Ltd, as recorded in the current tracker release.
- Does Queensland Hunter Gas Pipeline serve an LNG terminal?
- Queensland Hunter Gas Pipeline passes within 25 km of 1 tracked LNG terminal. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.
More gas pipelines in Australia
Listed in name order among the 148 pipelines tracked in Australia, so projects with the same name sit together. A browse aid, not a claim that they are alike.
- Reedy Creek Wallumbilla PipelineQueensland to Queensland · 50 km
- Riverland Pipeline SystemSouth Australia to South Australia · 237 km
- Roma to Brisbane PipelineQueensland to Queensland · 438 km
- Project Haber Gas PipelineWestern Australia to Western Australia · 120 km
- Queensland Gas PipelineQueensland to Queensland · 629 km
- Queensland Hunter Gas PipelineQueensland to New South Wales · 833 km
Cite this page
Reuse is welcome; please name the page and the tracker release it draws on.