Gas transmission pipeline · Guamaré to Cabo de Santo Agostinho
Nordestão Gas Pipeline
Nordestão Gas Pipeline is an operating gas transmission pipeline in Brazil. The tracker lists 1 tracked segment, 427 km long and 0.83 bcm/y of capacity, starting up in 1986. It runs from Guamaré to Cabo de Santo Agostinho. It is owned by CDPQ, ENGIE SA and Engie Brasil Energia.
Length
427 km
Capacity
0.83 bcm/y
0.6 Mtpa LNG equivalent
Segments tracked
1
Largest diameter 305 mm (12 in)
Route
Nordestão Gas Pipeline runs from Guamaré to Cabo de Santo Agostinho. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Guamaré
- To
- Cabo de Santo Agostinho
- Start country
- Brazil
- End country
- Brazil
- Countries crossed
- Brazil
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Americas
- Route drawn on map
- 482 km
- GEM pipeline ID
- P3135
- Start year
- 1986
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Whole pipeline | Operating | Guamaré → Cabo de Santo Agostinho | 427 | 0.83 | 305 mm | 1986 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
| Terminal | Country | Import / export | Status | Distance | Matched by |
|---|---|---|---|---|---|
| Suape FSRU | Brazil | Import | Under construction | 16.5 km | route proximity |
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Owners
- CDPQ50%
- ENGIE SA32.5%
- Engie Brasil Energia17.5%
Parent companies
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does Nordestão Gas Pipeline run?
- Nordestão Gas Pipeline runs from Guamaré to Cabo de Santo Agostinho, crossing Brazil.
- How long is Nordestão Gas Pipeline?
- Nordestão Gas Pipeline is 427 km long.
- How much gas can Nordestão Gas Pipeline carry?
- Nordestão Gas Pipeline has a design capacity of 0.83 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
- Is Nordestão Gas Pipeline operating?
- Nordestão Gas Pipeline is operating, having started in 1986.
- Who owns Nordestão Gas Pipeline?
- Nordestão Gas Pipeline is owned by CDPQ, ENGIE SA and Engie Brasil Energia, as recorded in the current tracker release.
- Does Nordestão Gas Pipeline serve an LNG terminal?
- Nordestão Gas Pipeline passes within 25 km of 1 tracked LNG terminal. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.