LNG Atlas

Gas transmission pipeline · Yamalo-Nenets Autonomus Okrug to Yamalo-Nenets Autonomus Okrug

Kharasaveyskoye–Bovanenkovskoye Gas Pipeline

Kharasaveyskoye–Bovanenkovskoye Gas Pipeline is an under construction gas transmission pipeline in Russia. The tracker lists 1 tracked segment, 106 km long and 32 bcm/y of capacity, starting up in 2024. It runs from Yamalo-Nenets Autonomus Okrug to Yamalo-Nenets Autonomus Okrug. It is owned by Gazprom PJSC.

Length

106 km

Capacity

32 bcm/y

23.5 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 35560 mm (1400 in)

Route

Kharasaveyskoye–Bovanenkovskoye Gas Pipeline runs from Yamalo-Nenets Autonomus Okrug to Yamalo-Nenets Autonomus Okrug. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Yamalo-Nenets Autonomus Okrug
To
Yamalo-Nenets Autonomus Okrug
Start country
Russia
End country
Russia
Countries crossed
Russia
Onshore / offshore
Not reported
Fuel
Gas
Region
Not reported
Route drawn on map
93 km
GEM pipeline ID
P3607
Start year
2024
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineUnder constructionYamalo-Nenets Autonomus Okrug → Yamalo-Nenets Autonomus Okrug1063235560 mm2024GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

No tracked LNG terminal lies within 25 km of this pipeline's route.

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Owners

Parent companies

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Kharasaveyskoye–Bovanenkovskoye Gas Pipeline run?
Kharasaveyskoye–Bovanenkovskoye Gas Pipeline runs from Yamalo-Nenets Autonomus Okrug to Yamalo-Nenets Autonomus Okrug, crossing Russia.
How long is Kharasaveyskoye–Bovanenkovskoye Gas Pipeline?
Kharasaveyskoye–Bovanenkovskoye Gas Pipeline is 106 km long.
How much gas can Kharasaveyskoye–Bovanenkovskoye Gas Pipeline carry?
Kharasaveyskoye–Bovanenkovskoye Gas Pipeline has a design capacity of 32 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is Kharasaveyskoye–Bovanenkovskoye Gas Pipeline operating?
Kharasaveyskoye–Bovanenkovskoye Gas Pipeline is under construction, with a reported start year of 2024.
Who owns Kharasaveyskoye–Bovanenkovskoye Gas Pipeline?
Kharasaveyskoye–Bovanenkovskoye Gas Pipeline is owned by Gazprom PJSC, as recorded in the current tracker release.

More gas pipelines in Russia

Listed in name order among the 266 pipelines tracked in Russia, so projects with the same name sit together. A browse aid, not a claim that they are alike.

Cite this page

Reuse is welcome; please name the page and the tracker release it draws on.

BibTeX
Share this page:XLinkedInFacebookBlueskyRedditEmail