Gas transmission pipeline · Ústí nad Labem Region to Bavaria
Gazela Pipeline
Gazela Pipeline is an operating gas transmission pipeline crossing Czechia, Germany. The tracker lists 1 tracked segment, 166 km long and 30 bcm/y of capacity, starting up in 2013. It runs from Ústí nad Labem Region to Bavaria. It is owned by Net4Gas.
Length
166 km
Capacity
30 bcm/y
22.1 Mtpa LNG equivalent
Segments tracked
1
Largest diameter 35560 mm (1400 in)
Route
Gazela Pipeline runs from Ústí nad Labem Region to Bavaria. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Ústí nad Labem Region
- To
- Bavaria
- Start country
- Czech Republic
- End country
- Germany
- Countries crossed
- Czechia, Germany
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Not reported
- Route drawn on map
- 153 km
- GEM pipeline ID
- P0698
- Start year
- 2013
- Estimated cost (GEM, US dollars)
- $425 million
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Whole pipeline | Operating | Ústí nad Labem Region → Bavaria | 166 | 30 | 35560 mm | 2013 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
No tracked LNG terminal lies within 25 km of this pipeline's route.
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Owners
- Net4Gas100%
Parent companies
In the news
Recent headlines that name Gazela Pipeline. Matched by name, so it is approximate. Titles and links only; we store no article text.
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does Gazela Pipeline run?
- Gazela Pipeline runs from Ústí nad Labem Region to Bavaria, crossing Czechia and Germany.
- How long is Gazela Pipeline?
- Gazela Pipeline is 166 km long.
- How much gas can Gazela Pipeline carry?
- Gazela Pipeline has a design capacity of 30 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
- Is Gazela Pipeline operating?
- Gazela Pipeline is operating, having started in 2013.
- Who owns Gazela Pipeline?
- Gazela Pipeline is owned by Net4Gas, as recorded in the current tracker release.
More gas pipelines in Czechia
Listed in name order among the 14 pipelines tracked in Czechia, so projects with the same name sit together. A browse aid, not a claim that they are alike.
Cite this page
Reuse is welcome; please name the page and the tracker release it draws on.