Gas transmission pipeline · La Mora to San Bernardo

GasAndes Pipeline

GasAndes Pipeline is an operating gas transmission pipeline crossing Argentina, Chile. The tracker lists 1 tracked segment, 533 km long and 3.94 bcm/y of capacity, starting up in 1997. It runs from La Mora to San Bernardo. It is owned by Aprovisionadora Global de Energía SA, CGC (Compañía General de Combustibles) and AES Corp.

Length

533 km

Capacity

3.94 bcm/y

2.9 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 610 mm (24 in)

Route

GasAndes Pipeline runs from La Mora to San Bernardo. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
La Mora
To
San Bernardo
Start country
Argentina
End country
Chile
Countries crossed
Argentina, Chile
Onshore / offshore
Not reported
Fuel
Gas
Region
Americas
Route drawn on map
724 km
GEM pipeline ID
P1287
Start year
1997
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineOperatingLa Mora → San Bernardo5333.94610 mm1997GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

TerminalCountryImport / exportStatusDistanceMatched by
Quintero LNG TerminalChileImportOperating0.4 kmroute proximity
Colbun FLNG TerminalChileImportCancelled3.5 kmroute proximity

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does GasAndes Pipeline run?
GasAndes Pipeline runs from La Mora to San Bernardo, crossing Argentina and Chile.
How long is GasAndes Pipeline?
GasAndes Pipeline is 533 km long.
How much gas can GasAndes Pipeline carry?
GasAndes Pipeline has a design capacity of 3.94 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is GasAndes Pipeline operating?
GasAndes Pipeline is operating, having started in 1997.
Who owns GasAndes Pipeline?
GasAndes Pipeline is owned by Aprovisionadora Global de Energía SA, CGC (Compañía General de Combustibles) and AES Corp, as recorded in the current tracker release.
Does GasAndes Pipeline serve an LNG terminal?
GasAndes Pipeline passes within 25 km of 2 tracked LNG terminals. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.