Gas transmission pipeline · Bir Rebaa Nord gas field to Menzel Ledjmet Est gas field
Bir Rebaa Nord–Menzel Ledjmet Est Gas Pipeline
Bir Rebaa Nord–Menzel Ledjmet Est Gas Pipeline is an operating gas transmission pipeline in Algeria. The tracker lists 1 tracked segment, 185 km long and 2.5 bcm/y of capacity, starting up in 2020. It runs from Bir Rebaa Nord gas field to Menzel Ledjmet Est gas field. It is owned by Sonatrach SpA.
Length
185 km
Capacity
2.5 bcm/y
1.8 Mtpa LNG equivalent
Segments tracked
1
Largest diameter 406 mm (16 in)
Route
Bir Rebaa Nord–Menzel Ledjmet Est Gas Pipeline runs from Bir Rebaa Nord gas field to Menzel Ledjmet Est gas field. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Bir Rebaa Nord gas field
- To
- Menzel Ledjmet Est gas field
- Start country
- Algeria
- End country
- Algeria
- Countries crossed
- Algeria
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Africa
- Route drawn on map
- 143 km
- GEM pipeline ID
- P2052
- Start year
- 2020
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Whole pipeline | Operating | Bir Rebaa Nord gas field → Menzel Ledjmet Est gas field | 185 | 2.5 | 406 mm | 2020 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
No tracked LNG terminal lies within 25 km of this pipeline's route.
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Owners
- Sonatrach SpA100%
Parent companies
- Sonatrach SpA100%
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does Bir Rebaa Nord–Menzel Ledjmet Est Gas Pipeline run?
- Bir Rebaa Nord–Menzel Ledjmet Est Gas Pipeline runs from Bir Rebaa Nord gas field to Menzel Ledjmet Est gas field, crossing Algeria.
- How long is Bir Rebaa Nord–Menzel Ledjmet Est Gas Pipeline?
- Bir Rebaa Nord–Menzel Ledjmet Est Gas Pipeline is 185 km long.
- How much gas can Bir Rebaa Nord–Menzel Ledjmet Est Gas Pipeline carry?
- Bir Rebaa Nord–Menzel Ledjmet Est Gas Pipeline has a design capacity of 2.5 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
- Is Bir Rebaa Nord–Menzel Ledjmet Est Gas Pipeline operating?
- Bir Rebaa Nord–Menzel Ledjmet Est Gas Pipeline is operating, having started in 2020.
- Who owns Bir Rebaa Nord–Menzel Ledjmet Est Gas Pipeline?
- Bir Rebaa Nord–Menzel Ledjmet Est Gas Pipeline is owned by Sonatrach SpA, as recorded in the current tracker release.