Gas transmission pipeline · Mangystau Region to Turkistan Region
Beineu-Bozoy-Shymkent Gas Pipeline
Beineu-Bozoy-Shymkent Gas Pipeline is an operating gas transmission pipeline in Kazakhstan. The tracker lists 1 tracked segment, 1,449 km long and 15 bcm/y of capacity, starting up in 2013. It runs from Mangystau Region to Turkistan Region. It is owned by QazaqGaz and Trans-Asia Gas Pipeline Co Ltd.
Length
1,449 km
Capacity
15 bcm/y
11.0 Mtpa LNG equivalent
Segments tracked
1
Largest diameter 27102 mm (1067 in)
Route
Beineu-Bozoy-Shymkent Gas Pipeline runs from Mangystau Region to Turkistan Region. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Mangystau Region
- To
- Turkistan Region
- Start country
- Kazakhstan
- End country
- Kazakhstan
- Countries crossed
- Kazakhstan
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Not reported
- Route drawn on map
- 1,425 km
- GEM pipeline ID
- P3273
- Start year
- 2013
- Estimated cost (GEM, US dollars)
- $3.6 billion
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| I | Operating | Mangystau Region → Turkistan Region | 1,449 | 15 | 27102 mm | 2013 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
No tracked LNG terminal lies within 25 km of this pipeline's route.
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Owners
Parent companies
In the news
Recent headlines that name Beineu-Bozoy-Shymkent Gas Pipeline. Matched by name, so it is approximate. Titles and links only; we store no article text.
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does Beineu-Bozoy-Shymkent Gas Pipeline run?
- Beineu-Bozoy-Shymkent Gas Pipeline runs from Mangystau Region to Turkistan Region, crossing Kazakhstan.
- How long is Beineu-Bozoy-Shymkent Gas Pipeline?
- Beineu-Bozoy-Shymkent Gas Pipeline is 1,449 km long.
- How much gas can Beineu-Bozoy-Shymkent Gas Pipeline carry?
- Beineu-Bozoy-Shymkent Gas Pipeline has a design capacity of 15 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
- Is Beineu-Bozoy-Shymkent Gas Pipeline operating?
- Beineu-Bozoy-Shymkent Gas Pipeline is operating, having started in 2013.
- Who owns Beineu-Bozoy-Shymkent Gas Pipeline?
- Beineu-Bozoy-Shymkent Gas Pipeline is owned by QazaqGaz and Trans-Asia Gas Pipeline Co Ltd, as recorded in the current tracker release.
More gas pipelines in Kazakhstan
Listed in name order among the 37 pipelines tracked in Kazakhstan, so projects with the same name sit together. A browse aid, not a claim that they are alike.
- Beineu-Bozoy-Shymkent Gas PipelineMangystau Region to Turkistan Region · 1,449 km
- Beineu-Bozoy-Shymkent Gas PipelineMangystau Region to Turkistan Region · 0 km
- Bukhara-Ural Gas PipelineAktobe Region to Aktobe Region · 165 km
- Almaty-Bayserke-Talgar Gas Pipeline62 km
- Almaty-Taldykorgan Gas Pipeline303 km
- Amangeldy-KS5 Gas PipelineKostanay to Jambyl · 193 km
Cite this page
Reuse is welcome; please name the page and the tracker release it draws on.