Ananjiv-Bohorodchani Gas Pipeline is an operating gas transmission pipeline crossing Ukraine, Moldova. The tracker lists 1 tracked segment, 333 km long and 9.1 bcm/y of capacity, starting up in 1987. It runs from Ananjiv to Bohorodchani. It is owned by Gas Transmission System Operator of Ukraine and SNTGN Transgaz SA.

Length

333 km

Capacity

9.1 bcm/y

6.7 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 1020 mm (40 in)

Route

Ananjiv-Bohorodchani Gas Pipeline runs from Ananjiv to Bohorodchani. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Ananjiv
To
Bohorodchani
Start country
Ukraine
End country
Ukraine
Countries crossed
Ukraine, Moldova
Onshore / offshore
Not reported
Fuel
Gas
Region
Europe
Route drawn on map
431 km
GEM pipeline ID
P1481
Start year
1987
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineOperatingAnanjiv → Bohorodchani3339.11020 mm1987GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

No tracked LNG terminal lies within 25 km of this pipeline's route.

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Ananjiv-Bohorodchani Gas Pipeline run?
Ananjiv-Bohorodchani Gas Pipeline runs from Ananjiv to Bohorodchani, crossing Ukraine and Moldova.
How long is Ananjiv-Bohorodchani Gas Pipeline?
Ananjiv-Bohorodchani Gas Pipeline is 333 km long.
How much gas can Ananjiv-Bohorodchani Gas Pipeline carry?
Ananjiv-Bohorodchani Gas Pipeline has a design capacity of 9.1 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is Ananjiv-Bohorodchani Gas Pipeline operating?
Ananjiv-Bohorodchani Gas Pipeline is operating, having started in 1987.
Who owns Ananjiv-Bohorodchani Gas Pipeline?
Ananjiv-Bohorodchani Gas Pipeline is owned by Gas Transmission System Operator of Ukraine and SNTGN Transgaz SA, as recorded in the current tracker release.