Gas transmission pipeline · Yelets to Dykanka
Yelets-Kursk-Dykanka Gas Pipeline
Yelets-Kursk-Dykanka Gas Pipeline is an operating gas transmission pipeline crossing Russia, Ukraine. The tracker lists 1 tracked segment, 298 km long and 23.73 bcm/y of capacity, starting up in 1984. It runs from Yelets to Dykanka. It is owned by Gazprom PJSC and Gas Transmission System Operator of Ukraine.
Length
298 km
Capacity
23.7 bcm/y
17.4 Mtpa LNG equivalent
Segments tracked
1
Largest diameter 1220 mm (48 in)
Route
Yelets-Kursk-Dykanka Gas Pipeline runs from Yelets to Dykanka. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Yelets
- To
- Dykanka
- Start country
- Russia
- End country
- Ukraine
- Countries crossed
- Russia, Ukraine
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Europe
- Route drawn on map
- 428 km
- GEM pipeline ID
- P0775
- Start year
- 1984
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Whole pipeline | Operating | Yelets → Dykanka | 298 | 23.7 | 1220 mm | 1984 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
No tracked LNG terminal lies within 25 km of this pipeline's route.
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Parent companies
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does Yelets-Kursk-Dykanka Gas Pipeline run?
- Yelets-Kursk-Dykanka Gas Pipeline runs from Yelets to Dykanka, crossing Russia and Ukraine.
- How long is Yelets-Kursk-Dykanka Gas Pipeline?
- Yelets-Kursk-Dykanka Gas Pipeline is 298 km long.
- How much gas can Yelets-Kursk-Dykanka Gas Pipeline carry?
- Yelets-Kursk-Dykanka Gas Pipeline has a design capacity of 23.7 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
- Is Yelets-Kursk-Dykanka Gas Pipeline operating?
- Yelets-Kursk-Dykanka Gas Pipeline is operating, having started in 1984.
- Who owns Yelets-Kursk-Dykanka Gas Pipeline?
- Yelets-Kursk-Dykanka Gas Pipeline is owned by Gazprom PJSC and Gas Transmission System Operator of Ukraine, as recorded in the current tracker release.