Gas transmission pipeline · Ukhta to Republic of Chuvashia
Ukhta-Cheboksary Gas Pipeline
Ukhta-Cheboksary Gas Pipeline is a shelved gas transmission pipeline in Russia. The tracker lists 1 tracked segment, 920 km long and 37 bcm/y of capacity. It runs from Ukhta to Republic of Chuvashia.
Length
920 km
Capacity
37 bcm/y
27.2 Mtpa LNG equivalent
Segments tracked
1
Largest diameter 1420 mm (56 in)
Route
Ukhta-Cheboksary Gas Pipeline runs from Ukhta to Republic of Chuvashia. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Ukhta
- To
- Republic of Chuvashia
- Start country
- Russia
- End country
- Russia
- Countries crossed
- Russia
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Europe
- Route drawn on map
- 959 km
- GEM pipeline ID
- P2437
- Start year
- Not reported
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Whole pipeline | Shelved | Ukhta → Republic of Chuvashia | 920 | 37 | 1420 mm | — | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
No tracked LNG terminal lies within 25 km of this pipeline's route.
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Parent companies
- Gazprom PJSC100%
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does Ukhta-Cheboksary Gas Pipeline run?
- Ukhta-Cheboksary Gas Pipeline runs from Ukhta to Republic of Chuvashia, crossing Russia.
- How long is Ukhta-Cheboksary Gas Pipeline?
- Ukhta-Cheboksary Gas Pipeline is 920 km long.
- How much gas can Ukhta-Cheboksary Gas Pipeline carry?
- Ukhta-Cheboksary Gas Pipeline has a design capacity of 37 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
- Is Ukhta-Cheboksary Gas Pipeline operating?
- Ukhta-Cheboksary Gas Pipeline is shelved.
- Who owns Ukhta-Cheboksary Gas Pipeline?
- Ownership of Ukhta-Cheboksary Gas Pipeline is not reported in the current tracker release.