Gas transmission pipeline · Songkhla Gas Separation Plant to Chana Power Plant
TTM Gas Separation Plant-Chana Gas Pipeline
TTM Gas Separation Plant-Chana Gas Pipeline is an operating gas transmission pipeline in Thailand. The tracker lists 1 tracked segment, 8 km long and 2.96 bcm/y of capacity, starting up in 2007. It runs from Songkhla Gas Separation Plant to Chana Power Plant. It is owned by PTT Public Co Ltd.
Length
7.6 km
Capacity
2.96 bcm/y
2.2 Mtpa LNG equivalent
Segments tracked
1
Largest diameter 508 mm (20 in)
Route
TTM Gas Separation Plant-Chana Gas Pipeline runs from Songkhla Gas Separation Plant to Chana Power Plant. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Songkhla Gas Separation Plant
- To
- Chana Power Plant
- Start country
- Thailand
- End country
- Thailand
- Countries crossed
- Thailand
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Asia
- Route drawn on map
- 27 km
- GEM pipeline ID
- P1122
- Start year
- 2007
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Whole pipeline | Operating | Songkhla Gas Separation Plant → Chana Power Plant | 7.6 | 2.96 | 508 mm | 2007 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
| Terminal | Country | Import / export | Status | Distance | Matched by |
|---|---|---|---|---|---|
| Songkhla FSRU | Thailand | Import | Cancelled | 4.9 km | route proximity |
| Chana LNG Terminal | Thailand | Import | Cancelled | 6 km | route proximity |
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Owners
Parent companies
- PTT PCL100%
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does TTM Gas Separation Plant-Chana Gas Pipeline run?
- TTM Gas Separation Plant-Chana Gas Pipeline runs from Songkhla Gas Separation Plant to Chana Power Plant, crossing Thailand.
- How long is TTM Gas Separation Plant-Chana Gas Pipeline?
- TTM Gas Separation Plant-Chana Gas Pipeline is 7.6 km long.
- How much gas can TTM Gas Separation Plant-Chana Gas Pipeline carry?
- TTM Gas Separation Plant-Chana Gas Pipeline has a design capacity of 2.96 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
- Is TTM Gas Separation Plant-Chana Gas Pipeline operating?
- TTM Gas Separation Plant-Chana Gas Pipeline is operating, having started in 2007.
- Who owns TTM Gas Separation Plant-Chana Gas Pipeline?
- TTM Gas Separation Plant-Chana Gas Pipeline is owned by PTT Public Co Ltd, as recorded in the current tracker release.
- Does TTM Gas Separation Plant-Chana Gas Pipeline serve an LNG terminal?
- TTM Gas Separation Plant-Chana Gas Pipeline passes within 25 km of 2 tracked LNG terminals. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.