Trans Europa Naturgas Pipeline is an operating gas transmission pipeline crossing Germany, Switzerland. The tracker lists 1 tracked segment, 505 km long and 9.25 bcm/y of capacity, starting up in 1974. It runs from Bocholtz interconnection to Wallbach interconnection. It is owned by TENP GmbH & Co KG.

Length

505 km

Capacity

9.25 bcm/y

6.8 Mtpa LNG equivalent

Segments tracked

1

Route

Trans Europa Naturgas Pipeline runs from Bocholtz interconnection to Wallbach interconnection. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Bocholtz interconnection
To
Wallbach interconnection
Start country
Germany
End country
Switzerland
Countries crossed
Germany, Switzerland
Onshore / offshore
Not reported
Fuel
Gas
Region
Europe
Route drawn on map
466 km
GEM pipeline ID
P0723
Start year
1974
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
TENP, TENP I, TENP IIOperatingBocholtz interconnection → Wallbach interconnection5059.251974GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

TerminalCountryImport / exportStatusDistanceMatched by
Punta Europa LNG TerminalEquatorial GuineaExportOperatingname match

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Trans Europa Naturgas Pipeline run?
Trans Europa Naturgas Pipeline runs from Bocholtz interconnection to Wallbach interconnection, crossing Germany and Switzerland.
How long is Trans Europa Naturgas Pipeline?
Trans Europa Naturgas Pipeline is 505 km long.
How much gas can Trans Europa Naturgas Pipeline carry?
Trans Europa Naturgas Pipeline has a design capacity of 9.25 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is Trans Europa Naturgas Pipeline operating?
Trans Europa Naturgas Pipeline is operating, having started in 1974.
Who owns Trans Europa Naturgas Pipeline?
Trans Europa Naturgas Pipeline is owned by TENP GmbH & Co KG, as recorded in the current tracker release.
Does Trans Europa Naturgas Pipeline serve an LNG terminal?
Trans Europa Naturgas Pipeline passes within 25 km of 1 tracked LNG terminal. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.