Gas transmission pipeline · Ballena gas fields to Maracaibo

Trans-Caribbean Gas Pipeline

Trans-Caribbean Gas Pipeline is a mothballed gas transmission pipeline crossing Venezuela, Colombia. The tracker lists 1 tracked segment, 224 km long and 5 bcm/y of capacity, starting up in 2007. It runs from Ballena gas fields to Maracaibo. It is owned by PDVSA.

Length

224 km

Capacity

5 bcm/y

3.7 Mtpa LNG equivalent

Segments tracked

1

Route

Trans-Caribbean Gas Pipeline runs from Ballena gas fields to Maracaibo. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Ballena gas fields
To
Maracaibo
Start country
Venezuela
End country
Colombia
Countries crossed
Venezuela, Colombia
Onshore / offshore
Not reported
Fuel
Gas
Region
Americas
Route drawn on map
177 km
GEM pipeline ID
P1269
Start year
2007
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineMothballedBallena gas fields → Maracaibo22452007GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

TerminalCountryImport / exportStatusDistanceMatched by
Ballena FSRUColombiaImportProposed18 kmroute proximity

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Owners

Parent companies

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Trans-Caribbean Gas Pipeline run?
Trans-Caribbean Gas Pipeline runs from Ballena gas fields to Maracaibo, crossing Venezuela and Colombia.
How long is Trans-Caribbean Gas Pipeline?
Trans-Caribbean Gas Pipeline is 224 km long.
How much gas can Trans-Caribbean Gas Pipeline carry?
Trans-Caribbean Gas Pipeline has a design capacity of 5 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is Trans-Caribbean Gas Pipeline operating?
Trans-Caribbean Gas Pipeline is mothballed, with a reported start year of 2007.
Who owns Trans-Caribbean Gas Pipeline?
Trans-Caribbean Gas Pipeline is owned by PDVSA, as recorded in the current tracker release.
Does Trans-Caribbean Gas Pipeline serve an LNG terminal?
Trans-Caribbean Gas Pipeline passes within 25 km of 1 tracked LNG terminal. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.