Gas transmission pipeline · Ohio to Michigan
Rover Pipeline
Rover Pipeline is an operating gas transmission pipeline in United States. The tracker lists 1 tracked segment, 1,144 km long and 17.37 bcm/y of capacity, starting up in 2017. It runs from Ohio to Michigan. It is owned by Energy Transfer LP, Blackstone and Traverse.
Length
1,144 km
Capacity
17.4 bcm/y
12.8 Mtpa LNG equivalent
Segments tracked
1
Largest diameter 1067 mm (42 in)
Route
Rover Pipeline runs from Ohio to Michigan. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Ohio
- To
- Michigan
- Start country
- United States
- End country
- United States
- Countries crossed
- United States
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Americas
- Route drawn on map
- 925 km
- GEM pipeline ID
- P0392
- Start year
- 2017
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Phase 1 | Operating | Ohio → Michigan | 1,144 | 17.4 | 1067 mm | 2017 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
No tracked LNG terminal lies within 25 km of this pipeline's route.
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Owners
- Traverse35%
- Energy Transfer LP32.57%
- Blackstone32.44%
Parent companies
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does Rover Pipeline run?
- Rover Pipeline runs from Ohio to Michigan, crossing United States.
- How long is Rover Pipeline?
- Rover Pipeline is 1,144 km long.
- How much gas can Rover Pipeline carry?
- Rover Pipeline has a design capacity of 17.4 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
- Is Rover Pipeline operating?
- Rover Pipeline is operating, having started in 2017.
- Who owns Rover Pipeline?
- Rover Pipeline is owned by Traverse, Energy Transfer LP and Blackstone, as recorded in the current tracker release.