Neuba II Gas Pipeline is an operating gas transmission pipeline in Argentina. The tracker lists 1 tracked segment, 38 km long and 1.83 bcm/y of capacity, starting up in 2023. It runs from Buenos Aires to Carlos Casares.
Length
38 km
Capacity
1.83 bcm/y
1.3 Mtpa LNG equivalent
Segments tracked
1
Largest diameter 914 mm (36 in)
Route
Neuba II Gas Pipeline runs from Buenos Aires to Carlos Casares. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Buenos Aires
- To
- Carlos Casares
- Start country
- Argentina
- End country
- Argentina
- Countries crossed
- Argentina
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Americas
- Route drawn on map
- 38 km
- GEM pipeline ID
- P5792
- Start year
- 2023
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Neuba II Loop | Operating | Buenos Aires → Carlos Casares | 38 | 1.83 | 914 mm | 2023 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
No tracked LNG terminal lies within 25 km of this pipeline's route.
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Ownership is not reported for this pipeline.
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does Neuba II Gas Pipeline run?
- Neuba II Gas Pipeline runs from Buenos Aires to Carlos Casares, crossing Argentina.
- How long is Neuba II Gas Pipeline?
- Neuba II Gas Pipeline is 38 km long.
- How much gas can Neuba II Gas Pipeline carry?
- Neuba II Gas Pipeline has a design capacity of 1.83 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
- Is Neuba II Gas Pipeline operating?
- Neuba II Gas Pipeline is operating, having started in 2023.
- Who owns Neuba II Gas Pipeline?
- Ownership of Neuba II Gas Pipeline is not reported in the current tracker release.