Gas transmission pipeline · Dornum to Steinitz

NETRA Gas Pipeline

NETRA Gas Pipeline is an operating gas transmission pipeline in Germany. The tracker lists 1 tracked segment, 408 km long and 21.4 bcm/y of capacity, starting up in 1995. It runs from Dornum to Steinitz. It is owned by NETRA GmbH Norddeutsche Erdgas Transversale & Co KG.

Length

408 km

Capacity

21.4 bcm/y

15.7 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 1200 mm (47 in)

Route

NETRA Gas Pipeline runs from Dornum to Steinitz. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Dornum
To
Steinitz
Start country
Germany
End country
Germany
Countries crossed
Germany
Onshore / offshore
Not reported
Fuel
Gas
Region
Europe
Route drawn on map
290 km
GEM pipeline ID
P0710
Start year
1995
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineOperatingDornum → Steinitz40821.41200 mm1995GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

TerminalCountryImport / exportStatusDistanceMatched by
Jade Energy LNG TerminalGermanyImportProposed11.3 kmroute proximity
Wilhelmshaven NWO FSRUGermanyImportCancelled11.3 kmroute proximity
Wilhelmshaven FSRUGermanyImportOperating14.8 kmroute proximity
Wilhelmshaven TES FSRUGermanyImportOperating14.9 kmroute proximity

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does NETRA Gas Pipeline run?
NETRA Gas Pipeline runs from Dornum to Steinitz, crossing Germany.
How long is NETRA Gas Pipeline?
NETRA Gas Pipeline is 408 km long.
How much gas can NETRA Gas Pipeline carry?
NETRA Gas Pipeline has a design capacity of 21.4 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is NETRA Gas Pipeline operating?
NETRA Gas Pipeline is operating, having started in 1995.
Who owns NETRA Gas Pipeline?
NETRA Gas Pipeline is owned by NETRA GmbH Norddeutsche Erdgas Transversale & Co KG, as recorded in the current tracker release.
Does NETRA Gas Pipeline serve an LNG terminal?
NETRA Gas Pipeline passes within 25 km of 4 tracked LNG terminals. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.