Gas transmission pipeline · Groundbirch to Summit Lake
Merrick Mainline Pipeline
Merrick Mainline Pipeline is a cancelled gas transmission pipeline in Canada. The tracker lists 1 tracked segment, 260 km long and 20.44 bcm/y of capacity, starting up in 2020. It runs from Groundbirch to Summit Lake. It is owned by TC Energy Corp.
Length
260 km
Capacity
20.4 bcm/y
15.0 Mtpa LNG equivalent
Segments tracked
1
Largest diameter 1219 mm (48 in)
Route
Merrick Mainline Pipeline runs from Groundbirch to Summit Lake. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Groundbirch
- To
- Summit Lake
- Start country
- Canada
- End country
- Canada
- Countries crossed
- Canada
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Americas
- Route drawn on map
- 253 km
- GEM pipeline ID
- P0332
- Start year
- 2020
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Whole pipeline | Cancelled | Groundbirch → Summit Lake | 260 | 20.4 | 1219 mm | 2020 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
| Terminal | Country | Import / export | Status | Distance | Matched by |
|---|---|---|---|---|---|
| Summit Lake PG LNG Terminal | Canada | Export | Proposed | 11.5 km | route proximity |
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Owners
- TC Energy Corp100%
Parent companies
- TC Energy Corp100%
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does Merrick Mainline Pipeline run?
- Merrick Mainline Pipeline runs from Groundbirch to Summit Lake, crossing Canada.
- How long is Merrick Mainline Pipeline?
- Merrick Mainline Pipeline is 260 km long.
- How much gas can Merrick Mainline Pipeline carry?
- Merrick Mainline Pipeline has a design capacity of 20.4 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
- Is Merrick Mainline Pipeline operating?
- Merrick Mainline Pipeline is cancelled, with a reported start year of 2020.
- Who owns Merrick Mainline Pipeline?
- Merrick Mainline Pipeline is owned by TC Energy Corp, as recorded in the current tracker release.
- Does Merrick Mainline Pipeline serve an LNG terminal?
- Merrick Mainline Pipeline passes within 25 km of 1 tracked LNG terminal. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.