LNG Atlas

Gas transmission pipeline · Trinidad and Tobago – Barbados – Martinique – Guadeloupe

Inter-Caribbean Natural Gas Pipeline

Inter-Caribbean Natural Gas Pipeline is a cancelled gas transmission pipeline crossing Trinidad and Tobago, Barbados, Martinique and 1 more. The tracker lists 1 tracked segment, 959 km long and 1.53 bcm/y of capacity. Owners include Beowulf Energy, First Reserve, Guardian Holdings and 2 more.

Length

959 km

Capacity

1.53 bcm/y

1.1 Mtpa LNG equivalent

Segments tracked

1

Route

Inter-Caribbean Natural Gas Pipeline runs from Trinidad and Tobago – Barbados – Martinique – Guadeloupe. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Not reported
To
Not reported
Start country
Trinidad and Tobago
End country
Guadeloupe
Countries crossed
Trinidad and Tobago, Barbados, Martinique, Guadeloupe
Onshore / offshore
Not reported
Fuel
Gas
Region
Not reported
Route drawn on map
568 km
GEM pipeline ID
P1259
Start year
Not reported
Shelved (year GEM records)
2012
Cancelled (year GEM records)
2014
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineCancelledNot reported9591.53——GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

No tracked LNG terminal lies within 25 km of this pipeline's route.

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Inter-Caribbean Natural Gas Pipeline run?
Inter-Caribbean Natural Gas Pipeline runs from Trinidad and Tobago to Guadeloupe, crossing Trinidad and Tobago, Barbados, Martinique and Guadeloupe.
How long is Inter-Caribbean Natural Gas Pipeline?
Inter-Caribbean Natural Gas Pipeline is 959 km long.
How much gas can Inter-Caribbean Natural Gas Pipeline carry?
Inter-Caribbean Natural Gas Pipeline has a design capacity of 1.53 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is Inter-Caribbean Natural Gas Pipeline operating?
Inter-Caribbean Natural Gas Pipeline is cancelled.
Who owns Inter-Caribbean Natural Gas Pipeline?
Inter-Caribbean Natural Gas Pipeline is owned by Beowulf Energy, First Reserve, Guardian Holdings and 2 others, as recorded in the current tracker release.

More gas pipelines in Trinidad and Tobago

Listed in name order among the 7 pipelines tracked in Trinidad and Tobago, so projects with the same name sit together. A browse aid, not a claim that they are alike.

Cite this page

Reuse is welcome; please name the page and the tracker release it draws on.