Gas transmission pipeline · Romania – Ukraine
Hust–Satu Mare Gas Pipeline
Hust–Satu Mare Gas Pipeline is an operating gas transmission pipeline crossing Romania, Ukraine. The tracker lists 1 tracked segment, 21 km long and 2 bcm/y of capacity, starting up in 1999. It is owned by Gas Transmission System Operator of Ukraine.
Length
21 km
Capacity
2 bcm/y
1.5 Mtpa LNG equivalent
Segments tracked
1
Largest diameter 18288 mm (720 in)
Route
Hust–Satu Mare Gas Pipeline runs from Romania – Ukraine. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Not reported
- To
- Not reported
- Start country
- Ukraine
- End country
- Romania
- Countries crossed
- Romania, Ukraine
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Not reported
- Route drawn on map
- 53 km
- GEM pipeline ID
- P1451
- Start year
- 1999
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Whole pipeline | Operating | Not reported | 21 | 2 | 18288 mm | 1999 | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
No tracked LNG terminal lies within 25 km of this pipeline's route.
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Parent companies
In the news
Recent headlines that name Hust–Satu Mare Gas Pipeline. Matched by name, so it is approximate. Titles and links only; we store no article text.
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does Hust–Satu Mare Gas Pipeline run?
- Hust–Satu Mare Gas Pipeline runs from Ukraine to Romania, crossing Romania and Ukraine.
- How long is Hust–Satu Mare Gas Pipeline?
- Hust–Satu Mare Gas Pipeline is 21 km long.
- How much gas can Hust–Satu Mare Gas Pipeline carry?
- Hust–Satu Mare Gas Pipeline has a design capacity of 2 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
- Is Hust–Satu Mare Gas Pipeline operating?
- Hust–Satu Mare Gas Pipeline is operating, having started in 1999.
- Who owns Hust–Satu Mare Gas Pipeline?
- Hust–Satu Mare Gas Pipeline is owned by Gas Transmission System Operator of Ukraine, as recorded in the current tracker release.
More gas pipelines in Romania