Gas transmission pipeline · Hassi R'Mel to Piombino
GALSI Pipeline
GALSI Pipeline is a shelved gas transmission pipeline crossing Algeria, Italy. The tracker lists 1 tracked segment, 861 km long and 8 bcm/y of capacity. It runs from Hassi R'Mel to Piombino. Owners include Sonatrach SpA, Edison SpA, Enel and 2 more.
Length
861 km
Capacity
8 bcm/y
5.9 Mtpa LNG equivalent
Segments tracked
1
Largest diameter 660 mm (26 in)
Route
GALSI Pipeline runs from Hassi R'Mel to Piombino. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Hassi R'Mel
- To
- Piombino
- Start country
- Algeria
- End country
- Italy
- Countries crossed
- Algeria, Italy
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Africa
- Route drawn on map
- 781 km
- GEM pipeline ID
- P0697
- Start year
- Not reported
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Whole pipeline | Shelved | Hassi R'Mel → Piombino | 861 | 8 | 660 mm | — | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
| Terminal | Country | Import / export | Status | Distance | Matched by |
|---|---|---|---|---|---|
| Piombino FSRU | Italy | Import | Operating | 3.5 km | route proximity |
| Portovesme FSRU | Italy | Import | Cancelled | 13.5 km | route proximity |
| Oristano FSRU | Italy | Import | Proposed | 21.5 km | route proximity |
| HIGAS LNG Terminal | Italy | Import | Operating | 21.6 km | route proximity |
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Owners
- Edison SpA20.8%
- Enel15.6%
- Government of Sardinia10.4%
- Hera Group10.4%
- Sonatrach SpA
Parent companies
- Edison SpA20.8%
- Enel15.6%
- Region of Sardinia10.4%
- Sonatrach SpA
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does GALSI Pipeline run?
- GALSI Pipeline runs from Hassi R'Mel to Piombino, crossing Algeria and Italy.
- How long is GALSI Pipeline?
- GALSI Pipeline is 861 km long.
- How much gas can GALSI Pipeline carry?
- GALSI Pipeline has a design capacity of 8 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
- Is GALSI Pipeline operating?
- GALSI Pipeline is shelved.
- Who owns GALSI Pipeline?
- GALSI Pipeline is owned by Edison SpA, Enel, Government of Sardinia and 2 others, as recorded in the current tracker release.
- Does GALSI Pipeline serve an LNG terminal?
- GALSI Pipeline passes within 25 km of 4 tracked LNG terminals. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.