LNG Chain

Gas transmission pipeline · CATS Riser Platform to Teesside

Central Area Transmission System (CATS) Gas Pipeline

Central Area Transmission System (CATS) Gas Pipeline is an operating gas transmission pipeline in United Kingdom. The tracker lists 1 tracked segment, 404 km long and 1.7 bcm/y of capacity, starting up in 1993. It runs from CATS Riser Platform to Teesside. It is owned by Kellas Midstream Ltd.

Length

404 km

Capacity

1.7 bcm/y

1.2 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 914 mm (36 in)

Route

Central Area Transmission System (CATS) Gas Pipeline runs from CATS Riser Platform to Teesside. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
CATS Riser Platform
To
Teesside
Start country
United Kingdom
End country
United Kingdom
Countries crossed
United Kingdom
Onshore / offshore
Not reported
Fuel
Gas
Region
Europe
Route drawn on map
404 km
GEM pipeline ID
P0686
Start year
1993
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineOperatingCATS Riser Platform → Teesside4041.7914 mm1993GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

TerminalCountryImport / exportStatusDistanceMatched by
Teesside WaveCrest LNG TerminalUnited KingdomImportProposed3.3 kmroute proximity
Teesside GasPort FSRUUnited KingdomImportProposed9.1 kmroute proximity
Central Java FSRUIndonesiaImportCancelledname match

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Central Area Transmission System (CATS) Gas Pipeline run?
Central Area Transmission System (CATS) Gas Pipeline runs from CATS Riser Platform to Teesside, crossing United Kingdom.
How long is Central Area Transmission System (CATS) Gas Pipeline?
Central Area Transmission System (CATS) Gas Pipeline is 404 km long.
How much gas can Central Area Transmission System (CATS) Gas Pipeline carry?
Central Area Transmission System (CATS) Gas Pipeline has a design capacity of 1.7 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is Central Area Transmission System (CATS) Gas Pipeline operating?
Central Area Transmission System (CATS) Gas Pipeline is operating, having started in 1993.
Who owns Central Area Transmission System (CATS) Gas Pipeline?
Central Area Transmission System (CATS) Gas Pipeline is owned by Kellas Midstream Ltd, as recorded in the current tracker release.
Does Central Area Transmission System (CATS) Gas Pipeline serve an LNG terminal?
Central Area Transmission System (CATS) Gas Pipeline passes within 25 km of 3 tracked LNG terminals. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.