LNG Chain

Gas transmission pipeline · Black sea shore to Podisor

Black Sea Shore-Podisor Pipeline

Black Sea Shore-Podisor Pipeline is an under construction gas transmission pipeline in Romania. The tracker lists 1 tracked segment, 308 km long and 14.82 bcm/y of capacity, starting up in 2027. It runs from Black sea shore to Podisor. It is owned by SNTGN Transgaz SA.

Length

308 km

Capacity

14.8 bcm/y

10.9 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 1219 mm (48 in)

Route

Black Sea Shore-Podisor Pipeline runs from Black sea shore to Podisor. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Black sea shore
To
Podisor
Start country
Romania
End country
Romania
Countries crossed
Romania
Onshore / offshore
Not reported
Fuel
Gas
Region
Europe
Route drawn on map
307 km
GEM pipeline ID
P1702
Start year
2027
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineUnder constructionBlack sea shore → Podisor30814.81219 mm2027GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

TerminalCountryImport / exportStatusDistanceMatched by
Constanta LNG TerminalRomaniaImportCancelled22.4 kmroute proximity

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Parent companies

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Black Sea Shore-Podisor Pipeline run?
Black Sea Shore-Podisor Pipeline runs from Black sea shore to Podisor, crossing Romania.
How long is Black Sea Shore-Podisor Pipeline?
Black Sea Shore-Podisor Pipeline is 308 km long.
How much gas can Black Sea Shore-Podisor Pipeline carry?
Black Sea Shore-Podisor Pipeline has a design capacity of 14.8 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is Black Sea Shore-Podisor Pipeline operating?
Black Sea Shore-Podisor Pipeline is under construction, with a reported start year of 2027.
Who owns Black Sea Shore-Podisor Pipeline?
Black Sea Shore-Podisor Pipeline is owned by SNTGN Transgaz SA, as recorded in the current tracker release.
Does Black Sea Shore-Podisor Pipeline serve an LNG terminal?
Black Sea Shore-Podisor Pipeline passes within 25 km of 1 tracked LNG terminal. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.