LNG Atlas

Gas transmission pipeline · Jordan

Arab Gas Pipeline

Arab Gas Pipeline is an operating gas transmission pipeline in Jordan. The tracker lists 1 tracked segment, 393 km long and 10.3 bcm/y of capacity, starting up in 2005. It is owned by Jordanian Egyptian Fajr Natural Gas Co.

Length

393 km

Capacity

10.3 bcm/y

7.6 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 914 mm (36 in)

Route

Arab Gas Pipeline runs from Jordan. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Aqaba
To
Not reported
Start country
Jordan
End country
Jordan
Countries crossed
Jordan
Onshore / offshore
Not reported
Fuel
Gas
Region
Not reported
Route drawn on map
387 km
GEM pipeline ID
P7511
Start year
2005
Estimated cost (GEM, US dollars)
$276 million
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Aqaba-Rihab Gas PipelineOperatingAqaba → ?39310.3914 mm2005GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

TerminalCountryImport / exportStatusDistanceMatched by
Sheikh Sabah LNG TerminalJordanImportProposed1.8 kmroute proximity
Aqaba Jordan FSRUJordanImportOperating1.9 kmroute proximity
Eilat FLNG TerminalIsraelExportCancelled8 kmroute proximity

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Arab Gas Pipeline run?
Arab Gas Pipeline is recorded in Jordan. Global Energy Monitor reports no start and end points for it.
How long is Arab Gas Pipeline?
Arab Gas Pipeline is 393 km long.
How much gas can Arab Gas Pipeline carry?
Arab Gas Pipeline has a design capacity of 10.3 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is Arab Gas Pipeline operating?
Arab Gas Pipeline is operating, having started in 2005.
Who owns Arab Gas Pipeline?
Arab Gas Pipeline is owned by Jordanian Egyptian Fajr Natural Gas Co, as recorded in the current tracker release.
Does Arab Gas Pipeline serve an LNG terminal?
Arab Gas Pipeline passes within 25 km of 3 tracked LNG terminals. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.

More gas pipelines in Jordan

Listed in name order among the 3 pipelines tracked in Jordan, so projects with the same name sit together. A browse aid, not a claim that they are alike.

Cite this page

Reuse is welcome; please name the page and the tracker release it draws on.

BibTeX
Share this page:XLinkedInFacebookBlueskyRedditEmail