Gas transmission pipeline · Mostaganem to Mostaganem
Aïn Nouïssy Gas Pipeline
Aïn Nouïssy Gas Pipeline is an operating gas transmission pipeline in Algeria. The tracker lists 1 tracked segment, 20 km long, starting up in 1973. It runs from Mostaganem to Mostaganem. It is owned by Sonatrach SpA.
Length
20 km
Capacity
Not reported
Segments tracked
1
Largest diameter 203 mm (8.0 in)
Route
No route geometry is available for this pipeline in the current release, so it is not drawn on the map. Start and end points below are shown where GEM reports them.
- From
- Mostaganem
- To
- Mostaganem
- Start country
- Algeria
- End country
- Algeria
- Countries crossed
- Algeria
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Not reported
- Route drawn on map
- Not reported
- GEM pipeline ID
- P7518
- Start year
- 1973
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Whole pipeline | Operating | Mostaganem → Mostaganem | 20 | Not reported | 203 mm | 1973 | No route |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
No tracked LNG terminal lies within 25 km of this pipeline's route.
Owners and operators
Stakes as reported by GEM per segment, merged across segments.
Owners
- Sonatrach SpA100%
In the news
Recent headlines that name Aïn Nouïssy Gas Pipeline. Matched by name, so it is approximate. Titles and links only; we store no article text.
Common questions
Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.
- Where does Aïn Nouïssy Gas Pipeline run?
- Aïn Nouïssy Gas Pipeline runs from Mostaganem to Mostaganem, crossing Algeria.
- How long is Aïn Nouïssy Gas Pipeline?
- Aïn Nouïssy Gas Pipeline is 20 km long.
- How much gas can Aïn Nouïssy Gas Pipeline carry?
- No design capacity is reported for Aïn Nouïssy Gas Pipeline. That is an absent figure, not a zero.
- Is Aïn Nouïssy Gas Pipeline operating?
- Aïn Nouïssy Gas Pipeline is operating, having started in 1973.
- Who owns Aïn Nouïssy Gas Pipeline?
- Aïn Nouïssy Gas Pipeline is owned by Sonatrach SpA, as recorded in the current tracker release.
More gas pipelines in Algeria
Listed in name order among the 125 pipelines tracked in Algeria, so projects with the same name sit together. A browse aid, not a claim that they are alike.
- Ain-Bessem Gas Pipeline14 km
- Alrar-Hassi R'Mel Gas PipelineIlizi to Laghouat · 966 km
- Alrar-Hassi R'Mel Gas PipelineIlizi to Laghouat · 966 km
- Aïn El Hadjel-M'Sila-Magra Gas PipelineM'Sila to M'Sila · 65 km
- Aïn El Ibel Gas PipelineDjelfa to Djelfa · 30 km
- Ain Madhi-Tadjemout Gas PipelineTadjemout to Tadjemout · 36 km