LNG Atlas

Gas transmission pipeline · Mediterranean Sea to Atlantic

Nador West Med Port-GME Gas Pipeline

Nador West Med Port-GME Gas Pipeline is a proposed gas transmission pipeline in Morocco. The tracker lists 1 tracked segment, 132 km long and 7.67 bcm/y of capacity. It runs from Mediterranean Sea to Atlantic.

Length

132 km

Capacity

7.67 bcm/y

5.6 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 1219 mm (48 in)

Route

No route geometry is available for this pipeline in the current release, so it is not drawn on the map. Start and end points below are shown where GEM reports them.

From
Mediterranean Sea
To
Atlantic
Start country
Morocco
End country
Morocco
Countries crossed
Morocco
Onshore / offshore
Not reported
Fuel
Gas
Region
Not reported
Route drawn on map
Not reported
GEM pipeline ID
P7611
Start year
Not reported
GEM wiki page
Not reported

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineProposedMediterranean Sea → Atlantic1327.671219 mm—No route

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

TerminalCountryImport / exportStatusDistanceMatched by
West Delta LNG Deepwater Port TerminalUnited StatesExportProposed—name match

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Ownership is not reported for this pipeline.

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Nador West Med Port-GME Gas Pipeline run?
Nador West Med Port-GME Gas Pipeline runs from Mediterranean Sea to Atlantic, crossing Morocco.
How long is Nador West Med Port-GME Gas Pipeline?
Nador West Med Port-GME Gas Pipeline is 132 km long.
How much gas can Nador West Med Port-GME Gas Pipeline carry?
Nador West Med Port-GME Gas Pipeline has a design capacity of 7.67 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is Nador West Med Port-GME Gas Pipeline operating?
Nador West Med Port-GME Gas Pipeline is proposed.
Who owns Nador West Med Port-GME Gas Pipeline?
Ownership of Nador West Med Port-GME Gas Pipeline is not reported in the current tracker release.
Does Nador West Med Port-GME Gas Pipeline serve an LNG terminal?
Nador West Med Port-GME Gas Pipeline passes within 25 km of 1 tracked LNG terminal. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.

More gas pipelines in Morocco

Listed in name order among the 4 pipelines tracked in Morocco, so projects with the same name sit together. A browse aid, not a claim that they are alike.