LNG Chain

Gas transmission pipeline · Haynesville to Gillis

Haynesville Global Access Pipeline

Haynesville Global Access Pipeline is a cancelled gas transmission pipeline in United States. The tracker lists 1 tracked segment, 258 km long and 20.44 bcm/y of capacity, starting up in 2023. It runs from Haynesville to Gillis. It is owned by Tellurian Inc.

Length

258 km

Capacity

20.4 bcm/y

15.0 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 1067 mm (42 in)

Route

Haynesville Global Access Pipeline runs from Haynesville to Gillis. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Haynesville
To
Gillis
Start country
United States
End country
United States
Countries crossed
United States
Onshore / offshore
Not reported
Fuel
Gas
Region
Americas
Route drawn on map
310 km
GEM pipeline ID
P0285
Start year
2023
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineCancelledHaynesville → Gillis25820.41067 mm2023GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

No tracked LNG terminal lies within 25 km of this pipeline's route.

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Owners

Parent companies

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Haynesville Global Access Pipeline run?
Haynesville Global Access Pipeline runs from Haynesville to Gillis, crossing United States.
How long is Haynesville Global Access Pipeline?
Haynesville Global Access Pipeline is 258 km long.
How much gas can Haynesville Global Access Pipeline carry?
Haynesville Global Access Pipeline has a design capacity of 20.4 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is Haynesville Global Access Pipeline operating?
Haynesville Global Access Pipeline is cancelled, with a reported start year of 2023.
Who owns Haynesville Global Access Pipeline?
Haynesville Global Access Pipeline is owned by Tellurian Inc, as recorded in the current tracker release.