LNG Atlas

Gas transmission pipeline · Gulf of Mexico to Gulf of Mexico

Delfin Offshore Pipeline

Delfin Offshore Pipeline is a proposed gas transmission pipeline in United States. The tracker lists 1 tracked segment, 0 km long and 6.72 bcm/y of capacity, starting up in 2027. It runs from Gulf of Mexico to Gulf of Mexico. It is owned by Delfin LNG LLC.

Length

0.2 km

Capacity

6.72 bcm/y

4.9 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 1067 mm (42 in)

Route

Delfin Offshore Pipeline runs from Gulf of Mexico to Gulf of Mexico. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Gulf of Mexico
To
Gulf of Mexico
Start country
United States
End country
United States
Countries crossed
United States
Onshore / offshore
Not reported
Fuel
Gas
Region
Not reported
Route drawn on map
0.5 km
GEM pipeline ID
P0173
Start year
2027
Estimated cost (GEM, US dollars)
$8 billion
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineProposedGulf of Mexico → Gulf of Mexico0.26.721067 mm2027GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

TerminalCountryImport / exportStatusDistanceMatched by
Delfin FLNG TerminalUnited StatesExportProposed—name match
UTM Offshore FLNG TerminalNigeriaExportProposed—name match
Venezuela Offshore LNG TerminalVenezuelaExportCancelled—name match

Owners and operators

Stakes as reported by GEM per segment, merged across segments.

Common questions

Generated from the same tracker fields as the tables above, so the two cannot disagree. Each answer stands on its own.

Where does Delfin Offshore Pipeline run?
Delfin Offshore Pipeline runs from Gulf of Mexico to Gulf of Mexico, crossing United States.
How long is Delfin Offshore Pipeline?
Delfin Offshore Pipeline is 0.2 km long.
How much gas can Delfin Offshore Pipeline carry?
Delfin Offshore Pipeline has a design capacity of 6.72 bcm/y. Where every segment of a project repeats the same figure it is counted once rather than summed.
Is Delfin Offshore Pipeline operating?
Delfin Offshore Pipeline is proposed, with a reported start year of 2027.
Who owns Delfin Offshore Pipeline?
Delfin Offshore Pipeline is owned by Delfin LNG LLC, as recorded in the current tracker release.
Does Delfin Offshore Pipeline serve an LNG terminal?
Delfin Offshore Pipeline passes within 25 km of 3 tracked LNG terminals. Proximity is not proof of a physical connection; each match is listed with its distance and how it was made.

More gas pipelines in United States

Listed in name order among the 515 pipelines tracked in United States, so projects with the same name sit together. A browse aid, not a claim that they are alike.

Cite this page

Reuse is welcome; please name the page and the tracker release it draws on.

BibTeX
Share this page:XLinkedInFacebookBlueskyRedditEmail